Export a GanttFather project to .xlsx, edit it in Excel and import it back. Shows which columns are read, which are not, and what the review step changes.
To export, open your project, click Import / export, choose Export project data and click Export Excel. You get an .xlsx file named after the project. To import, choose Import Excel in the same window, pick GanttFather format, upload the file and click Confirm Changes after you check the review screen.
Import and export run in your browser. Nothing is written to the project until you confirm the review.
Before you start
- Import needs a project you can edit. It is unavailable in a read-only project, such as a locked or archived one, and for Viewers. Export works in any project you can open.
- Import reads
.xlsxfiles only. A legacy.xlsfile must be opened in Excel and saved as.xlsxfirst.
How to export a project to Excel
- Open the project and click Import / export in the toolbar of the Gantt, List or Board view. The Data & sync window opens.
- Click Export project data.
- Click Export Excel.
- Open the downloaded file. It has one sheet named
Project_Plan.
You see the banner “Export downloaded successfully.” The sheet holds these columns. The file shows the headers in capital letters (for example LVL and TASK NAME), and import reads them in any case:
| Column | Header | What it holds |
|---|---|---|
| A | ID | Hidden task ID. Import uses it to match rows to tasks. |
| B | Lvl | Hierarchy depth: 0 for a top-level task, 1 for a subtask, and so on. |
| C | # | Outline number such as 1, 1.1, 1.2.1. |
| D | Task Name | Name, indented four spaces per level. |
| E | Owner | All assignee names, separated by commas. |
| F | Start Date | Start date. |
| G | End Date | Last day of the task, inclusive. |
| H | Progress | 0 to 100. |
| I | Status | The status name. |
| J onward | Timeline | One column per day with a painted bar. Import ignores it. |
How to import an Excel file
- Click Import / export, then Import Excel.
- Choose GanttFather format for a file exported from GanttFather or built the same way. (For a Microsoft Project file, see how to move a Microsoft Project schedule into GanttFather.)
- Click Next: View guide. Read the column reference, then click Next: Upload file.
- Drop the
.xlsxfile in the box, or click it to browse. GanttFather reads the file. - On the Confirm Import screen, check the tabs: New, Updated, Unchanged, Resources and Issues. Use Import into to place the imported tasks inside an existing task instead of at the top level.
- Click Confirm Changes.
When it finishes you see “Import complete” and a count such as “12 tasks created · 3 tasks updated.” Click Close.
What is imported
| Imported | How it is read |
|---|---|
| Task name | Required. A row with an empty name is skipped and listed under Issues. |
| Hierarchy | From Lvl if it is filled. Otherwise from the # outline number (the dots set the depth). Otherwise from leading spaces in the name. A row nests at most one level below the row above it. |
| Start and end | Excel dates, 2026-01-15, or 15/01/2026 (day/month/year). A blank end date becomes the start date. An unreadable start date becomes today and shows a warning. |
| Progress | 0 to 100. Values from 0 to 1 are read as fractions, so 0.5 is 50% and 1 is 100%. Values above 100 become 100. |
| Status | Matched by name against your project statuses, ignoring case. Common words such as done, closed and on hold also work. A blank cell uses the default status. |
| Owner | Matched by full name against members and resources. A name that does not exist yet is created as a virtual resource, and the Resources tab lists these before you confirm. |
Columns are found by their header text, so extra columns do not break the import.
What is not imported
- Dependencies, priority, description, effort, bar colors and icons are not in the Excel round trip. Set them in GanttFather.
- Tasks missing from the sheet are never deleted. Import only creates and updates.
- If you move or reorder an existing task in the sheet, the review shows it as updated, but only its field values change. The move is not applied. New tasks keep the sheet’s hierarchy.
- A status that does not exist in the project is not created. The task gets the default “not started” status and the row shows a warning. Create the status in Project Settings first.
What happens next
Before it writes anything, GanttFather saves a restore point named “Before Excel import”. After the import you can open History, then Versions, to roll the project back. The restore point is saved only for Owners and Admins. An Editor’s import still runs without it.
Re-importing a file you exported and did not change creates and updates nothing. If a row matches a task by ID, or by its parent chain and name, the task is updated. Otherwise a new task is created. Importing a file exported from a different project creates every row as a new task when the names differ.
Imported tasks get a random bar color.
Common problems
- “That doesn’t look like an Excel file.” The file is not
.xlsx. Save it as an Excel Workbook and upload it again. - “Legacy .xls files can’t be read.” Open the file in Excel, save it as
.xlsx, and upload it again. Invalid Template: Missing "Project_Plan" sheet. In GanttFather format the sheet must be namedProject_Plan. Rename the sheet, or use MS Project format if the file came from Microsoft Project.- All tasks land at the top level. The
Lvlcolumn was deleted or empty and there is no#column. Fill inLvlor the outline numbers. - Import stops partway with a rate-limit message. Large files send many requests. Wait about a minute and click Try again. Rows already imported are recognized and updated, not duplicated.
Related guides
- How to move a Microsoft Project schedule into GanttFather
- How to save and restore a version in GanttFather
- How to make a Gantt chart in Excel
- GanttFather features
- Alternatives to Excel for a project schedule
Can you move a plan between Excel and GanttFather?
Yes. Export your project to .xlsx to share it, back it up or edit names, dates and owners in bulk, then import the file and check the review screen before anything is saved. A restore point is saved first, so a bad import can be rolled back from History.
Import and export are included in every GanttFather project. Dependencies, priority and descriptions stay inside GanttFather, so keep working there after the first import.
Open a free GanttFather project and import your Excel plan to see the review screen with your own tasks.
Frequently asked questions
Can I edit an exported file in Excel and import it again?
Yes. Keep the Project_Plan sheet name, the hidden ID column and the Lvl column. Changed names, dates, progress, status and owners show as updated on the review screen. Parent tasks take their status and dates from their subtasks, so changes to those two fields count only on tasks without subtasks.
Does import delete tasks that are not in the file?
No. Import only creates and updates tasks.
Can I import a .xls or .csv file?
No. Import reads .xlsx files only. Open the file in Excel and save it as .xlsx first.
Want to skip the reading?
GanttFather is free forever, with no card and no trial.