Repeat a task on a schedule with the arrow next to New task, change one repeat or the whole series, and copy a task with Duplicate or Ctrl+D.
To repeat a task on a schedule, click the arrow next to New task, choose Recurring task…, set the name, start date and repeat rule, and click Create. GanttFather creates one task per date. To copy one task, select it and press Ctrl+D in the Gantt view, or choose Duplicate from its menu.
Both features shipped in GanttFather 0.31.1 on 22 October 2026.
Before you start
- You need to be an Owner, Admin or Editor of the project. Viewers and read-only projects do not show these controls.
- A recurring task cannot be placed under a task linked to Azure DevOps.
How to create a recurring task
- Open the project in the Gantt, List or Board view.
- Click the arrow to the right of New task (its label is “More ways to create”), then choose Recurring task…. The New recurring task dialog opens.
- Type a Name.
- Under Assign to, type a name to add people. Only the people you choose are assigned.
- Set Starts, Each task lasts (in working days or weeks) and, if you want, Effort per task in hours.
- Open Repeat and choose Every working day, Daily, Weekly, Monthly, Yearly or Custom…. The presets take their day from the start date, so a Wednesday start repeats every Wednesday.
- Optional: under Subtasks, add the steps every task should get, such as “Prepare agenda”. Under Place under, choose where the series goes.
- Check the line under the repeat field. It states how many tasks you get and the first and last date, for example “2 tasks, 21 Oct to 23 Nov”. Click Create 2 tasks.
You see a series row on the chart with one task under it for each date. Each task is a normal task with its own dates, people, status and progress.
Custom… opens a page inside the same dialog. You choose to repeat every 1 to 99 days, weeks, months or years, the weekdays for weekly rules, the day of the month (a day number, the nth weekday, or the first or last working day), and the end. The end is When the project ends, On a date, or After a number of times. You also choose what happens on a non-working day: Move it to the next working day or Skip that date.
How a series behaves
- A series has an end and holds at most 100 tasks (500 including subtasks). “When the project ends” means the last day of the latest-ending task at the moment you create the series. If the project has no dated task yet, choose an end date or a number of times.
- Dragging, resizing or editing one task changes only that task. The toast says “Only this task changed.”
- To change every task, open a task’s details, switch What to edit to Whole series, make the change and click Apply. A preview titled “What Apply will do” lists the dates that move and the tasks that stay as they are before anything changes.
- Tasks that are done, already started, or changed by hand stay as they are unless you choose Change it too. On a hand-edited task, Reset returns it to the series value.
- To stop repeating, open the series and choose Stop repeating…. The tasks stay as ordinary tasks.
- Deleting a task of a series asks This task or The whole series.
- A subtask you add to one task asks This task only or Every task in the series.
How to duplicate a task
- Select the task.
- Use one of these:
- In the Gantt view, press Ctrl+D (⌘D on a Mac).
- Click the arrow next to New task and choose Duplicate followed by the task name.
- Open the row menu (Gantt), use the Duplicate action on the row (List), or open the card menu (Board).
- Open the task details and choose Duplicate from the more-actions menu.
- The copy appears directly below the original, named “name (copy)”. In the Gantt view its name opens for editing.
The copy keeps the name, dates, people, priority, color, effort, description and parent. It does not keep status or progress (it starts at the default status and 0%), dependencies, attachments, history or Azure DevOps links. A toast offers Undo, and Ctrl+Z also undoes the copy.
Common problems
- No arrow next to New task. You are a guest or the project is read-only. Ask an Owner or Admin for edit access.
- Duplicate is unavailable. A task with subtasks cannot be duplicated yet. The menu says “Duplicating a group with its subtasks is not available yet”. Duplicate the subtasks one by one.
- The Create button is disabled. The line in the dialog body says why: no name, no date fits the rule, more than 100 tasks, or a subtask without a name.
- Ctrl+D does nothing. The shortcut works in the Gantt view only, with a row selected and the focus outside a text field. In the List and Board views use the row or card menu.
- You cannot add a subtask under a series row. A series holds only its own tasks. Add the subtask to one of them.
Related guides
- How to read a Gantt chart
- How to save and restore a version in GanttFather
- How to import and export Excel in GanttFather
- GanttFather features
Can GanttFather schedule repeating tasks?
Yes. Create a recurring task from the arrow next to New task, pick a rule such as every Wednesday or the last working day of each month, and GanttFather creates each repeat as a task you can move, assign or finish on its own. Change the whole series from the task details after you see what will move.
Use Duplicate for one-off copies of a task, such as a standard checklist you reuse in each phase.
Open a free GanttFather project and create your first recurring task to see the series on the chart.
Frequently asked questions
Can I change every task in a series at once?
Yes. Open a task’s details, switch to Whole series, make the change and click Apply. Done, started and hand-edited tasks are kept as they are.
How many repeats can a series have?
Up to 100 tasks, or 500 counting their subtasks.
Does Duplicate copy dependencies?
No. The copy keeps dates, people, priority, color, effort and description, but not dependencies, status, progress or attachments.
Want to skip the reading?
GanttFather is free forever, with no card and no trial.