Events & experiences Project timeline template

Trade show planning

Best for preparing one exhibitor presence with booth, logistics, staffing, promotion, and lead handoff.

Best for preparing one exhibitor presence with booth, logistics, staffing, promotion, and lead handoff.

Use this finite event plan to make the critical handoffs visible before delivery.

Trade show planning: Use this finite event plan to make the critical handoffs visible before delivery.

Best for preparing one exhibitor presence with booth, logistics, staffing, promotion, and lead handoff. The schedule moves through Show commitment, Exhibit preparation and Show delivery, making decisions, handoffs, and closeout visible before the event advances.

After creating the project, set real dates and accountable owners. Use Confirm show commitment, Set exhibitor goals and Show plan approved as starting checkpoints, and keep Attendee leads, Booth contracts, Shipping account details, Payment details, Staff travel details and Show portal credentials in the secured project.

Schedule

16 Rows, 10 Dependencies.

Schedule: Confirm show commitment, Set exhibitor goals, Show plan approved.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
Week 5
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
19Day
20Day
21Day
22Day
23Day
Confirm show commitment
Set exhibitor goals
Design booth experience
Prepare show collateral
Arrange booth logistics
Confirm booth staffing
Promote show presence
Complete booth teardown
Qualify and hand off leads

Use this finite event plan to make the critical handoffs visible before delivery.

Schedule

Schedule Rows

Trade show planning: Use this finite event plan to make the critical handoffs visible before delivery.

Work itemTypeScheduleDurationDepends on
Show commitment Phase Days 1–5 Derived rollup —
Confirm show commitment Task Days 1–2 2 working days —
Set exhibitor goals Task Days 3–4 2 working days Confirm show commitment
Show plan approved Milestone Day 5 Milestone Set exhibitor goals
Exhibit preparation Phase Days 6–13 Derived rollup —
Design booth experience Task Days 6–9 4 working days —
Prepare show collateral Task Days 6–10 5 working days —
Arrange booth logistics Task Days 10–12 3 working days Design booth experience
Exhibit ready Milestone Day 13 Milestone Prepare show collateral, Arrange booth logistics
Show delivery Phase Days 14–23 Derived rollup —
Confirm booth staffing Task Days 14–15 2 working days —
Promote show presence Task Days 14–16 3 working days —
Booth open Milestone Day 17 Milestone Promote show presence, Confirm booth staffing
Complete booth teardown Task Days 18–19 2 working days Booth open
Qualify and hand off leads Task Days 20–22 3 working days Complete booth teardown
Lead handoff complete Milestone Day 23 Milestone Qualify and hand off leads

Event teams

  • Event teams: Trade show planning
  • Event teams: Show commitment, Exhibit preparation, Show delivery

Schedule

  • Show commitment: Confirm show commitment, Set exhibitor goals and Show plan approved
  • Exhibit preparation: Design booth experience, Arrange booth logistics, Prepare show collateral and Exhibit ready
  • Show delivery: Confirm booth staffing, Promote show presence, Booth open, Complete booth teardown, Qualify and hand off leads and Lead handoff complete

Template guidance

  • Set the real event date, accountable owners, and decision deadlines after creation.
  • Use Confirm show commitment, Set exhibitor goals and Show plan approved as starting checkpoints, then add venue- and team-specific work.
  • Keep Attendee leads, Booth contracts, Shipping account details, Payment details, Staff travel details and Show portal credentials in the secured project instead of this public planning template.

Planning guidance

Trade show planning: Use this finite event plan to make the critical handoffs visible before delivery.

  1. 1

    Show commitment

    Use Show commitment to make the next decision and handoff visible before event work moves forward.

  2. 2

    Exhibit preparation

    Use Exhibit preparation to make the next decision and handoff visible before event work moves forward.

  3. 3

    Show delivery

    Use Show delivery to make the next decision and handoff visible before event work moves forward.

Keep private details in your project

Good to know

This public template for Trade show planning organizes a bounded schedule; it does not store operational records or private event data. Keep Attendee leads, Booth contracts, Shipping account details, Payment details, Staff travel details and Show portal credentials in the secured project.

  • Attendee leads
  • Booth contracts
  • Payment details
  • Shipping account details
  • Show portal credentials
  • Staff travel details

Template FAQ

Good to know

What does the Trade show planning template include?

It organizes Show commitment, Exhibit preparation and Show delivery into a finite schedule with named work, dependencies, and decision points.

Who should use the Trade show planning template?

Event teams: Trade show planning. Event teams: Show commitment, Exhibit preparation, Show delivery.

How should I adapt the Trade show planning template?

Set real dates and owners, add event-specific work, and keep Attendee leads, Booth contracts, Shipping account details, Payment details, Staff travel details and Show portal credentials in the secured project.

Related templates

Related templates

Use this template free

Set the real event date, accountable owners, and decision deadlines after creation.

Use this template free: Trade show planning

Use this finite event plan to make the critical handoffs visible before delivery.