Research Project timeline template

Thesis and dissertation

Best for planning one thesis or dissertation from an approved proposal through research, drafting, review-ready work, and submission.

Best for planning one thesis or dissertation from an approved proposal through research, drafting, review-ready work, and submission.

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

Thesis and dissertation: How to use this template.

Thesis and dissertation: How to use this template.

Best for planning one thesis or dissertation from an approved proposal through research, drafting, review-ready work, and submission.

Proposal and scope

Confirm thesis proposal, Define research plan, Proposal ready for research

Research and drafting

Collect and organize research evidence, Draft core chapters, Integrate supervisor feedback, Draft manuscript ready

Review and submit

Prepare review-ready manuscript, Run final manuscript review, Submit thesis or dissertation, Thesis manuscript submitted for review

Adapt after creation

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

Schedule

14 Rows, 8 Dependencies.

Thesis and dissertation: Best for planning one thesis or dissertation from an approved proposal through research, drafting, review-ready work, and submission.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
19Day
20Day
21Day
22Day
23Day
24Day
25Day
26Day
27Day
28Day
Confirm thesis proposal
Define research plan
Collect and organize research evidence
Draft core chapters
Integrate supervisor feedback
Prepare review-ready manuscript
Run final manuscript review

Use the interactive schedule to inspect the planned sequence.

Schedule details

Schedule details

Proposal and scope, Research and drafting, Review and submit

Work itemTypeScheduleDurationDepends on
Proposal and scope Phase Days 1–6 Derived rollup —
Confirm thesis proposal Task Days 1–3 3 working days —
Define research plan Task Days 4–5 2 working days Confirm thesis proposal
Proposal ready for research Milestone Day 6 Milestone Define research plan
Research and drafting Phase Days 7–21 Derived rollup —
Collect and organize research evidence Task Days 7–11 5 working days —
Draft core chapters Task Days 12–17 6 working days Collect and organize research evidence
Integrate supervisor feedback Task Days 18–20 3 working days Draft core chapters
Draft manuscript ready Milestone Day 21 Milestone Integrate supervisor feedback
Review and submit Phase Days 22–28 Derived rollup —
Prepare review-ready manuscript Task Days 22–24 3 working days —
Run final manuscript review Task Days 25–26 2 working days Prepare review-ready manuscript
Submit thesis or dissertation Task Day 27 1 working day Run final manuscript review
Thesis manuscript submitted for review Milestone Day 28 Milestone Submit thesis or dissertation

Who this helps

  • Who this helps
  • Research Planning team

What is included

  • Proposal and scope: Confirm thesis proposal → Proposal ready for research
  • Research and drafting: Collect and organize research evidence → Draft manuscript ready
  • Review and submit: Prepare review-ready manuscript → Thesis manuscript submitted for review

Adapt after creation

  • Relative working days show planned order, not calendar dates.
  • Not included: Student records, Supervisor feedback.

How to use this template

Thesis and dissertation: How to use this template

  1. 1

    Proposal and scope

    Confirm thesis proposal, Define research plan, Proposal ready for research

  2. 2

    Research and drafting

    Collect and organize research evidence, Draft core chapters, Integrate supervisor feedback, Draft manuscript ready

  3. 3

    Review and submit

    Prepare review-ready manuscript, Run final manuscript review, Submit thesis or dissertation, Thesis manuscript submitted for review

Not included

Planning boundary

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

  • Institutional approval documents
  • Private manuscript drafts
  • Repository credentials
  • Research participant data
  • Student records
  • Supervisor feedback

Frequently asked questions

Good to know

Thesis and dissertation: Frequently asked questions

What is included: Proposal and scope, Research and drafting, Review and submit.

Good to know

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

Related templates

Templates

Ready to adapt this plan?

Relative working days show planned order, not calendar dates.

Use this template free: Thesis and dissertation

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.