Research Project timeline template

Grant proposal

Best for developing one grant proposal from a selected opportunity through internal review and a documented submission or withdrawal.

Best for developing one grant proposal from a selected opportunity through internal review and a documented submission or withdrawal.

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

Grant proposal: How to use this template.

Grant proposal: How to use this template.

Best for developing one grant proposal from a selected opportunity through internal review and a documented submission or withdrawal.

Opportunity foundation

Select funding opportunity, Confirm proposal requirements, Opportunity and requirements recorded

Develop proposal

Define project work plan, Prepare budget inputs, Draft proposal narrative, Run internal proposal review, Submission package ready

Submit and close

Submit proposal, Record submission or withdrawal, Proposal cycle closed

Adapt after creation

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

Schedule

14 Rows, 8 Dependencies.

Grant proposal: Best for developing one grant proposal from a selected opportunity through internal review and a documented submission or withdrawal.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
Select funding opportunity
Confirm proposal requirements
Define project work plan
Prepare budget inputs
Draft proposal narrative
Run internal proposal review

Use the interactive schedule to inspect the planned sequence.

Schedule details

Schedule details

Opportunity foundation, Develop proposal, Submit and close

Work itemTypeScheduleDurationDepends on
Opportunity foundation Phase Days 1–5 Derived rollup —
Select funding opportunity Task Days 1–2 2 working days —
Confirm proposal requirements Task Days 3–4 2 working days Select funding opportunity
Opportunity and requirements recorded Milestone Day 5 Milestone Confirm proposal requirements
Develop proposal Phase Days 6–15 Derived rollup —
Define project work plan Task Days 6–8 3 working days —
Prepare budget inputs Task Days 6–8 3 working days —
Draft proposal narrative Task Days 9–12 4 working days Prepare budget inputs, Define project work plan
Run internal proposal review Task Days 13–14 2 working days Draft proposal narrative
Submission package ready Milestone Day 15 Milestone Run internal proposal review
Submit and close Phase Days 16–18 Derived rollup —
Submit proposal Task Day 16 1 working day —
Record submission or withdrawal Task Day 17 1 working day Submit proposal
Proposal cycle closed Milestone Day 18 Milestone Record submission or withdrawal

Who this helps

  • Who this helps
  • Research Planning team

What is included

  • Opportunity foundation: Select funding opportunity → Opportunity and requirements recorded
  • Develop proposal: Define project work plan → Submission package ready
  • Submit and close: Submit proposal → Proposal cycle closed

Adapt after creation

  • Relative working days show planned order, not calendar dates.
  • Not included: Funder portal credentials, Applicant contact data.

How to use this template

Grant proposal: How to use this template

  1. 1

    Opportunity foundation

    Select funding opportunity, Confirm proposal requirements, Opportunity and requirements recorded

  2. 2

    Develop proposal

    Define project work plan, Prepare budget inputs, Draft proposal narrative, Run internal proposal review, Submission package ready

  3. 3

    Submit and close

    Submit proposal, Record submission or withdrawal, Proposal cycle closed

Not included

Planning boundary

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

  • Applicant contact data
  • Banking details
  • Funder portal credentials
  • Institutional budget details
  • Reviewer correspondence
  • Vendor quotes

Frequently asked questions

Good to know

Grant proposal: Frequently asked questions

What is included: Opportunity foundation, Develop proposal, Submit and close.

Good to know

This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

Related templates

Templates

Ready to adapt this plan?

Relative working days show planned order, not calendar dates.

Use this template free: Grant proposal