Software & technology Project timeline template

Software Release Timeline

Plan a software release from scope through deployment with a practical 19-working-day schedule.

Best for planning and delivering a software release.

Your first project is included. Existing accounts stay subject to their available project capacity.

A software release plan that makes handoffs visible before delivery pressure builds.

Use this software release timeline template when a release needs a visible path from scope to deployment. It separates planning, build work, and launch checks so product, engineering, and QA can agree on scope, quality, and launch handoffs before work starts.

The schedule starts with scope and backlog preparation, moves through implementation and QA planning, then closes with regression testing, release notes, and deployment. The approval and completion milestones make the decisions between those stages easy to find in the Gantt chart.

This is a starting plan rather than a deployment system. After creating the project, assign owners, set the real dates, and add the environment-specific work that belongs to your team.

Included schedule

13 rows, 7 links, already sequenced.

A read-only preview of the published version. Click a bar, double-click it, or press Enter in the preview to inspect it.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
19Day
20Day
Define scope
Prepare backlog
Implement work
Prepare QA plan
Run regression testing
Write release notes

Read-only shared Gantt preview. Click or focus a bar and press Enter to inspect it.

Schedule details

Complete schedule table

The same published schedule is available below as a semantic table for detailed review.

Work itemTypeScheduleDurationDepends on
Plan Phase Days 1–6 Derived rollup
Define scope Task Days 1–2 2 working days
Prepare backlog Task Days 3–5 3 working days Define scope
Plan approved Milestone Day 6 Milestone Prepare backlog
Build Phase Days 7–14 Derived rollup
Implement work Task Days 7–13 7 working days
Prepare QA plan Task Days 7–9 3 working days
Feature complete Milestone Day 14 Milestone Implement work, Prepare QA plan
Launch Phase Days 15–20 Derived rollup
Run regression testing Task Days 15–18 4 working days
Write release notes Task Days 15–16 2 working days
Deploy release Task Day 19 1 working day Run regression testing, Write release notes
Released Milestone Day 20 Milestone Deploy release

Who it helps

  • Product managers coordinating a release
  • Engineering and QA leads aligning handoffs

What is included

  • Scope and backlog preparation
  • Implementation and QA planning
  • Regression testing, release notes, and deployment

Adapt it after creation

  • Set the start date to your release window
  • Rename work items for your product and owners
  • Add team-specific review or approval steps after creation

How to use this template

A practical path through the schedule.

  1. 1

    Confirm the release plan

    Define scope, prepare the backlog, and use the Plan approved milestone to establish what is ready to enter delivery.

  2. 2

    Coordinate build and quality work

    Run implementation alongside QA planning, then use Feature complete as the shared handoff into launch preparation.

  3. 3

    Ship with visible launch checks

    Sequence regression testing, release notes, deployment, and the release milestone so the final steps are not managed from memory.

Not included

Planning aid

This template is a planning aid and does not replace your team's release, security, or deployment procedures.

  • Azure and GitHub links
  • CI/CD credentials
  • Environments
  • Release artifacts
  • Source repositories
  • Sprint capacity
  • Story points

Template FAQ

Answers before you start.

What does this software release timeline template include?

It includes planning, implementation, QA preparation, regression testing, release notes, deployment, and release milestones arranged in one dependency-aware schedule.

Who should use this release schedule?

It is a practical starting point for product managers, engineering leads, and QA leads who need one view of the handoffs required to ship a software release.

Can this template be adapted for our release process?

Yes. After creating the project, set a real start date, assign owners, rename work for your product, and add your environment-specific approvals or deployment steps.

Related templates

Templates

Ready to adapt this schedule?

Create an editable project, set a real start date, and make the plan your own.

Use this template free

Your first project is included. Existing accounts stay subject to their available project capacity.