Software Release Timeline
Plan a software release from scope through deployment with a practical 19-working-day schedule.
Best for planning and delivering a software release.
Your first project is included. Existing accounts stay subject to their available project capacity.
A software release plan that makes handoffs visible before delivery pressure builds.
Use this software release timeline template when a release needs a visible path from scope to deployment. It separates planning, build work, and launch checks so product, engineering, and QA can agree on scope, quality, and launch handoffs before work starts.
The schedule starts with scope and backlog preparation, moves through implementation and QA planning, then closes with regression testing, release notes, and deployment. The approval and completion milestones make the decisions between those stages easy to find in the Gantt chart.
This is a starting plan rather than a deployment system. After creating the project, assign owners, set the real dates, and add the environment-specific work that belongs to your team.
Included schedule
13 rows, 7 links, already sequenced.
A read-only preview of the published version. Click a bar, double-click it, or press Enter in the preview to inspect it.
Read-only shared Gantt preview. Click or focus a bar and press Enter to inspect it.
Schedule details
Complete schedule table
The same published schedule is available below as a semantic table for detailed review.
| Work item | Type | Schedule | Duration | Depends on |
|---|---|---|---|---|
| Plan | Phase | Days 1–6 | Derived rollup | — |
| Define scope | Task | Days 1–2 | 2 working days | — |
| Prepare backlog | Task | Days 3–5 | 3 working days | Define scope |
| Plan approved | Milestone | Day 6 | Milestone | Prepare backlog |
| Build | Phase | Days 7–14 | Derived rollup | — |
| Implement work | Task | Days 7–13 | 7 working days | — |
| Prepare QA plan | Task | Days 7–9 | 3 working days | — |
| Feature complete | Milestone | Day 14 | Milestone | Implement work, Prepare QA plan |
| Launch | Phase | Days 15–20 | Derived rollup | — |
| Run regression testing | Task | Days 15–18 | 4 working days | — |
| Write release notes | Task | Days 15–16 | 2 working days | — |
| Deploy release | Task | Day 19 | 1 working day | Run regression testing, Write release notes |
| Released | Milestone | Day 20 | Milestone | Deploy release |
Who it helps
- Product managers coordinating a release
- Engineering and QA leads aligning handoffs
What is included
- Scope and backlog preparation
- Implementation and QA planning
- Regression testing, release notes, and deployment
Adapt it after creation
- Set the start date to your release window
- Rename work items for your product and owners
- Add team-specific review or approval steps after creation
How to use this template
A practical path through the schedule.
- 1
Confirm the release plan
Define scope, prepare the backlog, and use the Plan approved milestone to establish what is ready to enter delivery.
- 2
Coordinate build and quality work
Run implementation alongside QA planning, then use Feature complete as the shared handoff into launch preparation.
- 3
Ship with visible launch checks
Sequence regression testing, release notes, deployment, and the release milestone so the final steps are not managed from memory.
Not included
Planning aid
This template is a planning aid and does not replace your team's release, security, or deployment procedures.
- Azure and GitHub links
- CI/CD credentials
- Environments
- Release artifacts
- Source repositories
- Sprint capacity
- Story points
Template FAQ
Answers before you start.
What does this software release timeline template include?
It includes planning, implementation, QA preparation, regression testing, release notes, deployment, and release milestones arranged in one dependency-aware schedule.
Who should use this release schedule?
It is a practical starting point for product managers, engineering leads, and QA leads who need one view of the handoffs required to ship a software release.
Can this template be adapted for our release process?
Yes. After creating the project, set a real start date, assign owners, rename work for your product, and add your environment-specific approvals or deployment steps.
Related templates
Close cousins.
Marketing Campaign Timeline
Coordinate brief, creative, launch QA, and performance review in a practical campaign schedule.
Client Delivery Plan
Manage discovery, delivery, review, and handoff with a client-facing project timeline.
Ready to adapt this schedule?
Create an editable project, set a real start date, and make the plan your own.
Use this template freeYour first project is included. Existing accounts stay subject to their available project capacity.