Professional services Project timeline template

Client Delivery Plan

Manage discovery, delivery, review, and handoff with a client-facing project timeline.

Best for managing a client engagement from discovery through handoff.

Your first project is included. Existing accounts stay subject to their available project capacity.

A client delivery plan that carries agreed work from discovery through approval and handoff.

Use this client delivery plan template to make every handoff from kickoff through client approval easier to see. The schedule protects the sequence from requirements through approval, including room for review and revisions before the final handoff.

It begins with a short discovery phase, turns agreed requirements into a delivery plan, and then gives the client review and revision cycle its own place in the schedule. That makes the approval path explicit instead of treating it as a final administrative step.

The public template intentionally does not contain client data, contracts, invoices, or private files. Add those details only in the project you create for the engagement.

Included schedule

14 rows, 9 links, already sequenced.

A read-only preview of the published version. Click a bar, double-click it, or press Enter in the preview to inspect it.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
Week 5
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
19Day
20Day
21Day
22Day
23Day
24Day
25Day
Gather requirements
Create work plan
Execute delivery
Midpoint review
Client review
Apply revisions
Handoff

Read-only shared Gantt preview. Click or focus a bar and press Enter to inspect it.

Schedule details

Complete schedule table

The same published schedule is available below as a semantic table for detailed review.

Work itemTypeScheduleDurationDepends on
Discovery Phase Days 1–5 Derived rollup
Project kickoff Milestone Day 1 Milestone
Gather requirements Task Days 2–4 3 working days Project kickoff
Requirements approved Milestone Day 5 Milestone Gather requirements
Delivery Phase Days 6–16 Derived rollup
Create work plan Task Days 6–7 2 working days
Execute delivery Task Days 8–15 8 working days Create work plan
Midpoint review Task Days 12–13 2 working days Create work plan
Delivery ready Milestone Day 16 Milestone Execute delivery, Midpoint review
Acceptance Phase Days 17–25 Derived rollup
Client review Task Days 17–19 3 working days
Apply revisions Task Days 20–22 3 working days Client review
Client approval Milestone Day 23 Milestone Apply revisions
Handoff Task Days 24–25 2 working days Client approval

Who it helps

  • Client services teams managing agreed deliverables
  • Project managers coordinating reviews and handoff

What is included

  • Kickoff and requirements approval
  • Work planning, execution, and midpoint review
  • Client review, revisions, approval, and handoff

Adapt it after creation

  • Replace generic work with the agreed deliverables
  • Add named owners and client review dates
  • Add contract-specific acceptance steps after creation

How to use this template

A practical path through the schedule.

  1. 1

    Establish an approved foundation

    Start at kickoff, gather requirements, and use Requirements approved to clarify what the delivery team is taking forward.

  2. 2

    Manage the delivery window

    Create the work plan, execute delivery, and run a midpoint review before the Delivery ready milestone.

  3. 3

    Finish with acceptance and handoff

    Keep client review, revisions, approval, and handoff linked so the final delivery path remains clear to the team and client.

Not included

Planning aid

This template is a planning aid and does not replace client contracts, acceptance criteria, or professional advice.

  • Client contacts and members
  • Contracts
  • Credentials
  • Invoices
  • Payment details
  • Private deliverables and files
  • Time billing

Template FAQ

Answers before you start.

What does this client delivery plan template include?

It includes kickoff, requirements approval, work planning, execution, midpoint review, client review, revisions, client approval, and handoff.

Is this template suitable for a client-facing project?

Yes. It is designed for teams that need a clear sequence from discovery through acceptance, while leaving the project-specific deliverables and client details for the private project.

What should I add after creating the delivery plan?

Add the agreed deliverables, named owners, client review dates, and any contract-specific acceptance steps that apply to the engagement.

Related templates

Templates

Ready to adapt this schedule?

Create an editable project, set a real start date, and make the plan your own.

Use this template free

Your first project is included. Existing accounts stay subject to their available project capacity.