Marketing & growth Project timeline template

Marketing Campaign Timeline

Coordinate brief, creative, launch QA, and performance review in a practical campaign schedule.

Best for planning, producing, and launching a marketing campaign.

Your first project is included. Existing accounts stay subject to their available project capacity.

A campaign timeline that connects the brief, creative approval, launch QA, and performance review.

Use this marketing campaign timeline template to give a team one visible sequence for the work that happens before and immediately after launch. It moves from the brief and audience definition through creative production and approval, then into configuration, launch QA, and performance review.

The schedule makes two decisions easy to see: whether the campaign plan is approved and whether the creative is approved. Those gates keep launch work from advancing on assumptions while still leaving room to tailor the plan to your channels.

Create the project to make it yours. Add channel-specific tasks, real spend and ownership information, and the reporting cadence your team uses; those details are deliberately not included in a public starter schedule.

Included schedule

14 rows, 9 links, already sequenced.

A read-only preview of the published version. Click a bar, double-click it, or press Enter in the preview to inspect it.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
Week 5
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
19Day
20Day
21Day
22Day
23Day
24Day
Write campaign brief
Define target audience
Develop campaign concept
Produce creative assets
Write campaign copy
Configure campaign
Run launch QA
Review campaign performance

Read-only shared Gantt preview. Click or focus a bar and press Enter to inspect it.

Schedule details

Complete schedule table

The same published schedule is available below as a semantic table for detailed review.

Work itemTypeScheduleDurationDepends on
Plan Phase Days 1–5 Derived rollup —
Write campaign brief Task Days 1–2 2 working days —
Define target audience Task Days 3–4 2 working days Write campaign brief
Plan approved Milestone Day 5 Milestone Define target audience
Create Phase Days 6–14 Derived rollup —
Develop campaign concept Task Days 6–8 3 working days —
Produce creative assets Task Days 9–13 5 working days Develop campaign concept
Write campaign copy Task Days 9–11 3 working days Develop campaign concept
Creative approved Milestone Day 14 Milestone Produce creative assets, Write campaign copy
Launch Phase Days 15–24 Derived rollup —
Configure campaign Task Days 15–16 2 working days —
Run launch QA Task Days 17–18 2 working days Configure campaign
Campaign live Milestone Day 19 Milestone Run launch QA
Review campaign performance Task Days 20–24 5 working days Campaign live

Who it helps

  • Marketing managers launching coordinated campaigns
  • Creative and channel teams planning approvals

What is included

  • Campaign brief and audience definition
  • Creative concept, copy, and asset production
  • Configuration, launch QA, and performance review

Adapt it after creation

  • Add the channels and owners for this campaign
  • Adjust approval time to match your review process
  • Add reporting milestones after the first review

How to use this template

A practical path through the schedule.

  1. 1

    Lock the campaign direction

    Write the brief, define the target audience, and use Plan approved to confirm the work can move into production.

  2. 2

    Produce and approve creative

    Develop the concept, copy, and assets as connected work, with Creative approved marking the handoff to launch setup.

  3. 3

    Launch, check, and learn

    Configure the campaign, run launch QA, mark it live, and keep the first performance review in the same timeline.

Not included

Planning aid

This template is a planning aid and does not replace channel policy, legal review, or performance measurement practices.

  • Advertising and channel credentials
  • Audience and customer lists
  • External analytics accounts
  • Media spend
  • Publishing automation
  • Uploaded creative files

Template FAQ

Answers before you start.

What does this marketing campaign timeline template include?

It includes campaign planning, audience definition, creative concept and production, approval, configuration, launch QA, a go-live milestone, and performance review.

Is this campaign schedule for a specific marketing channel?

No. It is a channel-neutral starting plan. Add the channel-specific tasks, owners, approvals, and reporting cadence your campaign needs after creation.

When should a marketing team use this template?

Use it when a campaign has several contributors and a defined launch moment, especially when creative approval and launch checks need to be coordinated in one place.

Related templates

Templates

Ready to adapt this schedule?

Create an editable project, set a real start date, and make the plan your own.

Use this template free