monday.com includes Gantt view on Standard and higher plans. Dependencies, milestones, baselines, and critical-path access require higher tiers or have rollout conditions, so plan choice matters.
Does monday.com have a Gantt chart?
Yes. monday work management includes Gantt view and the Gantt dashboard widget on Standard, Pro, and Enterprise—not on Free or Basic. The view can display dated items as bars, group and filter work, show dependency arrows, shift connected tasks, share a view, and export a chart. Advanced scheduling access depends on the plan.
The important distinction is that seeing a Gantt chart and building a dependency-driven schedule are not the same entitlement. monday.com documents its Dependency Column on Pro and Enterprise, while Gantt view begins at Standard. Baselines are Pro/Enterprise, and milestones and critical-path controls are also documented for Pro/Enterprise; the separate critical-path article currently labels that feature a trial.
Plan availability verified: August 7, 2026. monday.com is actively rolling out dependency types and lead/lag, so confirm the feature in your account before buying solely for one control.
Which monday.com plan includes each Gantt feature?
| Gantt capability | Free | Basic | Standard | Pro | Enterprise |
|---|---|---|---|---|---|
| Gantt view / widget | No | No | Yes | Yes | Yes |
| Timeline view | No | No | Yes | Yes | Yes |
| Dependency Column | No | No | No | Yes | Yes |
| Dependency arrows | No | No | Bars only unless relationships exist elsewhere | Yes | Yes |
| Flexible / Strict / No action modes | No | No | No | Yes | Yes |
| Milestones in Gantt | No | No | No | Yes | Yes |
| Baseline snapshots | No | No | No | Yes | Yes |
| Critical-path display | No | No | No | Documented; trial status may change | Documented; trial status may change |
| Batch dependencies | No | No | No | No | Project boards, up to 50 selected tasks |
| Cross-project dependencies | No | No | No | No | Gradual release for eligible project boards |
The safest reading is: choose Standard for a visual dated timeline, Pro for a dependency-driven single-board schedule, and Enterprise for cross-project coordination and batch setup. Plan names, regional availability, seat blocks, and prices can change; check the official pricing page for a quote.
How do you add a Gantt view to a monday board?
- Open the board that contains the project work.
- Add a Date or Timeline column if the items do not already have scheduled dates.
- Fill dates for every task that should appear. A missing date produces no usable schedule bar.
- Select the + next to the board’s views.
- Choose Gantt from the view center.
- In Gantt settings, select the Date or Timeline columns to display.
- Choose grouping, labels, colors, time scale, and whether subitems should be shown.
- Save the view for the team.
For a portfolio-style dashboard, add a Gantt widget and connect the relevant boards. Access and the number of boards a dashboard can combine depend on the account plan.
How do you set up dependencies in monday.com?
Dependencies are configured on the board, then visualized in Gantt:
- On a Pro or Enterprise board, add the Dependency Column.
- Select the Date or Timeline column that dependencies should control.
- Choose Flexible, Strict, or No action mode.
- Fill a date range for every dependent item; linking items does not create missing dates.
- In a task’s dependency cell, choose the item it depends on.
- Select FS, SS, FF, or SF when dependency types are available in your account.
- Add positive lag for a delay or negative lag for overlap when lead/lag is available.
- Open Gantt and enable Show dependencies to display the arrows.
- Move one predecessor bar and verify the downstream behavior before applying the workflow to the whole board.
Only one Dependency Column can be added to a board. monday.com’s current rollout also means some eligible accounts may not yet display dependency types or lead/lag even when the documentation describes them.
What do Flexible, Strict, and No action modes do?
| Mode | What happens when a predecessor moves | Best for | Main risk |
|---|---|---|---|
| Flexible | Moves the dependent item only when dates would overlap | Teams that want to preserve existing gaps | A chain can retain more slack than expected |
| Strict | Shifts the dependent item by the same date change | Controlled project schedules | One delay can move a long chain |
| No action | Keeps dates unchanged and only shows the relationship | Advisory links or manually scheduled work | Visible dependency violations remain unresolved |
Strict mode is closest to automatic schedule propagation, but it is not resource leveling. monday.com does not assign a second available person or resolve over-allocation merely because dates shifted. Review workload separately after moving a large chain.
Dependencies also do not populate empty timelines. monday.com requires dates to exist first, or a Duration + Timeline combo that can establish the date range.
Which dependency types and lag rules are supported?
monday work management documents the four standard relationships:
| Type | Constraint | Example |
|---|---|---|
| Finish-to-start (FS) | Successor starts after predecessor finishes | Publish after final approval |
| Start-to-start (SS) | Successor starts after predecessor starts | Begin frontend and API work together |
| Finish-to-finish (FF) | Successor finishes after predecessor finishes | Finish training materials with product readiness |
| Start-to-finish (SF) | Successor finishes after predecessor starts | End legacy support after new support begins |
Finish-to-start is the default. In Strict mode, a positive lag creates a gap and a negative value creates lead or overlap. monday.com notes that dependency types and lead/lag are being gradually released, and that lead/lag currently belongs to monday work management rather than monday CRM or monday dev.
If those distinctions are new, read FS, SS, FF, and SF explained with examples before building the board.
Can monday.com show baselines and critical path?
Yes, but these are not Standard-plan features.
Baselines: Pro and Enterprise users can take a snapshot of the scheduled Timeline or Date column. The snapshot stays fixed while current dates move, and monday.com colors current items to show whether they remain on plan. Creating the baseline duplicates the time column and creates a Formula Column; deleting those generated columns also deletes the baseline.
Critical path: The Gantt settings can highlight critical-path items in red. monday.com’s Gantt documentation lists milestones and critical path for Pro/Enterprise, while its current critical-path support page calls the feature a trial whose future plan requirements may change. Verify the control in the intended account before making it a contractual reporting dependency.
Critical-path quality still depends on complete dates and dependencies. A red path calculated from missing relationships is visually precise but operationally incomplete.
What can monday.com’s Gantt view export and share?
monday.com can share a Gantt view through a shareable view or embed, subject to board and account permissions. The chart can also be exported to PDF or Excel from its export control.
The current PDF export limit is up to ten years of timeline and 640 items. Larger charts return an error, so filter to the decision-relevant work or split the schedule before export. A PDF is a snapshot, not an interactive schedule; stakeholders cannot inspect live task details or dependency changes inside it.
What are the practical limits of monday.com’s Gantt chart?
- Plan layering: Standard displays Gantt, but dependency scheduling begins on Pro.
- Dates first: relationships do not create dates for unscheduled tasks.
- One Dependency Column: a board cannot hold independent dependency networks in multiple columns.
- Rollout variability: dependency types, lead/lag, and cross-project features may not appear simultaneously in every account.
- Cross-project access: cross-project dependencies are an Enterprise capability and exclude some private, shareable, or closed-workspace scenarios.
- Batch limit: Enterprise batch dependencies support up to 50 selected tasks at once.
- Export ceiling: chart-only export is limited to 640 items and ten years.
- Work-management breadth: the product’s flexible boards and automations are a strength, but a highly customized board requires governance before it behaves like a consistent schedule.
These are not reasons to avoid monday.com. They are reasons to pilot the exact workflow and plan tier instead of treating every “Gantt included” label as equivalent.
When should you choose monday.com or GanttFather?
Choose monday.com when the team already runs work on monday boards and values forms, automations, integrations, dashboards, flexible columns, and cross-department workflows more than a schedule-first interface. Keeping the chart beside the source tasks reduces duplicate updates.
Choose a dedicated Gantt tool when most users need a simpler schedule surface, the free tier must include real dependency management, or many stakeholders need view-only access without paid seats.
| Decision | monday work management | GanttFather |
|---|---|---|
| Best fit | Broad configurable work management | Gantt-first project scheduling |
| First Gantt tier | Standard paid plan | Free first owned project |
| Dependency types | FS/SS/FF/SF on eligible Pro/Enterprise accounts | FS/SS/FF/SF plus lag included in the app |
| Baseline overlay | Pro/Enterprise | No dedicated schedule-baseline overlay currently |
| Critical path | Pro/Enterprise documentation; trial note applies | Included in the application |
| Automation ecosystem | Strong | Narrower; focused on scheduling |
| Free collaboration | Free account is limited to 2 seats and no Gantt | 2 editors on the free project; unlimited viewers and guests |
| AI-agent schedule access | monday has an MCP surface; availability and scope are separate from Gantt tier | Native MCP with read-only or read/write access |
GanttFather does not replace monday.com’s automation and departmental workflow platform, and it has no automatic resource leveling or dedicated baseline overlay. It is a qualified alternative when the schedule itself is the product the team needs. If one free owned project, two editor seats, and unlimited viewers and guests fit the team shape, create a free GanttFather project and test the same delayed dependency chain in both products.
How should you evaluate monday Gantt before rollout?
Create one representative board with 25–50 tasks, real subitems, four dependency types, a milestone, one delayed chain, and two teams. Then test:
- whether every intended user can open the Gantt under the proposed license;
- how Flexible and Strict modes handle the same delay;
- whether the current account has dependency types and lag enabled;
- whether baseline and critical-path results match a manually checked network;
- how external viewers receive the schedule;
- whether the 640-item export ceiling matters;
- whether board automations unexpectedly change dates or statuses.
The result should decide the tier. Do not upgrade an entire workspace because a demo board worked under a trial or temporary feature allowance.
What else do people ask about monday.com Gantt charts?
Is monday.com’s Gantt chart free?
No. Gantt view and the Gantt widget begin on the Standard plan. monday.com’s Free plan supports up to two seats and a small board set, but it does not include Gantt view. Basic also does not include Gantt.
Does monday Standard include dependencies?
monday.com’s Gantt view starts on Standard, but its current dependency documentation marks the Dependency Column as a Pro and Enterprise feature. Standard can display a dated Gantt; choose Pro or higher when dependency-driven date movement is required.
Does monday.com have all four dependency types?
Yes, monday work management documents FS, SS, FF, and SF. The feature is being gradually released, so an eligible account may not show it yet. Finish-to-start remains the default, and lead/lag availability has its own rollout note.
Can monday.com calculate a critical path?
Yes. monday.com’s Gantt can highlight a critical path, with current Gantt documentation assigning milestones and critical path to Pro/Enterprise. A separate support page labels critical path a trial, so future packaging may change.
Can monday.com create a Gantt baseline?
Yes. Baseline snapshots are available on Pro and Enterprise. monday.com duplicates the selected time column and adds a Formula Column to support comparison; deleting those columns removes the baseline.
Plan and feature access checked: August 7, 2026.