Product & design Project timeline template

UX research

Best for coordinating a bounded UX research project from Define research questions through Deliver product recommendations.

Best for running one bounded UX study from research questions through synthesized findings and recommendations.

Put Define research questions, Run research sessions, and Deliver product recommendations on one agreed path.

UX research: make the handoff from Define research questions to Deliver product recommendations visible.

The UX research template turns a finite product-design outcome into a visible path through Prepare, Conduct, and Deliver. It gives a multidisciplinary team a shared sequence rather than a collection of disconnected workshops or tickets.

The schedule connects Define research questions, Run research sessions, and Deliver product recommendations. Milestones such as Research study ready, Research insights approved, and Research findings delivered make the evidence or approval required for the next handoff easy to find.

After creating the project, replace relative days with real dates, assign accountable owners, and add internal details only where they belong. The public starter deliberately excludes Participant identities and Raw session recordings.

Included schedule

11 rows, 5 links, already sequenced.

Explore the UX research schedule to connect Define research questions, Run research sessions, and Deliver product recommendations.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
Define research questions
Recruit study participants
Run research sessions
Synthesize study evidence
Deliver product recommendations

Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

Schedule details

Complete schedule table

Put Define research questions, Run research sessions, and Deliver product recommendations on one agreed path.

Work itemTypeScheduleDurationDepends on
Prepare Phase Days 1–6 Derived rollup —
Define research questions Task Days 1–2 2 working days —
Recruit study participants Task Days 3–5 3 working days Define research questions
Research study ready Milestone Day 6 Milestone Recruit study participants
Conduct Phase Days 7–15 Derived rollup —
Run research sessions Task Days 7–11 5 working days —
Synthesize study evidence Task Days 12–14 3 working days Run research sessions
Research insights approved Milestone Day 15 Milestone Synthesize study evidence
Deliver Phase Days 16–18 Derived rollup —
Deliver product recommendations Task Days 16–17 2 working days —
Research findings delivered Milestone Day 18 Milestone Deliver product recommendations

Who it helps

  • Product managers and design leads responsible for UX research
  • Researchers, designers, and delivery partners aligning the Deliver product recommendations decision

What is included

  • Prepare: Define research questions, Recruit study participants, and Research study ready
  • Conduct: Run research sessions, Synthesize study evidence, and Research insights approved
  • Deliver: Deliver product recommendations and Research findings delivered

Adapt after creation

  • Add secured information represented by Participant identities and Raw session recordings.
  • Replace relative working days with the real project start date.
  • Assign one accountable owner to each handoff and approval.

How to use this template

UX research: make the handoff from Define research questions to Deliver product recommendations visible.

  1. 1

    Prepare

    Start with Define research questions and Recruit study participants so the opening handoff is explicit.

  2. 2

    Conduct

    Use Run research sessions and Synthesize study evidence to turn progress into a concrete approval.

  3. 3

    Deliver

    Finish with Deliver product recommendations and record Research findings delivered for the next accountable team.

Not included

Planning aid

This public planning aid contains no confidential research, contract, or production material. Add Participant identities and Raw session recordings only inside your secured project.

  • Participant identities
  • Raw session recordings

Template FAQ

Good to know

What does the UX research template include?

It sequences Prepare, Conduct, and Deliver around named work such as Define research questions, Run research sessions, and Deliver product recommendations.

Who should use this UX research plan?

It supports teams that need a finite delivery boundary and an explicit decision after Deliver product recommendations.

How should I adapt the schedule?

Set dates and owners after creation, then add protected details such as Participant identities and Raw session recordings.

Related templates

Templates

Use the UX research template free

Keep scope, evidence, and ownership connected before the work moves forward.

Use the UX research template free

Put Define research questions, Run research sessions, and Deliver product recommendations on one agreed path.