Best for coordinating a bounded Brand identity design project from Align brand brief through Package brand guidelines.

Best for creating one brand identity package from a clear brief through approval and final handoff.

Put Align brand brief, Create identity directions, and Package brand guidelines on one agreed path.

Brand identity design: make the handoff from Align brand brief to Package brand guidelines visible.

The Brand identity design template turns a finite product-design outcome into a visible path through Strategy, Explore, and Handoff. It gives a multidisciplinary team a shared sequence rather than a collection of disconnected workshops or tickets.

The schedule connects Align brand brief, Create identity directions, and Package brand guidelines. Milestones such as Brand strategy approved, Identity direction approved, and Brand identity handoff complete make the evidence or approval required for the next handoff easy to find.

After creating the project, replace relative days with real dates, assign accountable owners, and add internal details only where they belong. The public starter deliberately excludes Trademark filings and Final asset licenses.

Included schedule

11 rows, 5 links, already sequenced.

Explore the Brand identity design schedule to connect Align brand brief, Create identity directions, and Package brand guidelines.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
Week 5
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
19Day
20Day
21Day
Align brand brief
Map brand context
Create identity directions
Refine selected direction
Package brand guidelines

Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

Schedule details

Complete schedule table

Put Align brand brief, Create identity directions, and Package brand guidelines on one agreed path.

Work itemTypeScheduleDurationDepends on
Strategy Phase Days 1–6 Derived rollup —
Align brand brief Task Days 1–2 2 working days —
Map brand context Task Days 3–5 3 working days Align brand brief
Brand strategy approved Milestone Day 6 Milestone Map brand context
Explore Phase Days 7–16 Derived rollup —
Create identity directions Task Days 7–11 5 working days —
Refine selected direction Task Days 12–15 4 working days Create identity directions
Identity direction approved Milestone Day 16 Milestone Refine selected direction
Handoff Phase Days 17–21 Derived rollup —
Package brand guidelines Task Days 17–20 4 working days —
Brand identity handoff complete Milestone Day 21 Milestone Package brand guidelines

Who it helps

  • Product managers and design leads responsible for Brand identity design
  • Researchers, designers, and delivery partners aligning the Package brand guidelines decision

What is included

  • Strategy: Align brand brief, Map brand context, and Brand strategy approved
  • Explore: Create identity directions, Refine selected direction, and Identity direction approved
  • Handoff: Package brand guidelines and Brand identity handoff complete

Adapt after creation

  • Add secured information represented by Trademark filings and Final asset licenses.
  • Replace relative working days with the real project start date.
  • Assign one accountable owner to each handoff and approval.

How to use this template

Brand identity design: make the handoff from Align brand brief to Package brand guidelines visible.

  1. 1

    Strategy

    Start with Align brand brief and Map brand context so the opening handoff is explicit.

  2. 2

    Explore

    Use Create identity directions and Refine selected direction to turn progress into a concrete approval.

  3. 3

    Handoff

    Finish with Package brand guidelines and record Brand identity handoff complete for the next accountable team.

Not included

Planning aid

This public planning aid contains no confidential research, contract, or production material. Add Trademark filings and Final asset licenses only inside your secured project.

  • Final asset licenses
  • Trademark filings

Template FAQ

Good to know

What does the Brand identity design template include?

It sequences Strategy, Explore, and Handoff around named work such as Align brand brief, Create identity directions, and Package brand guidelines.

Who should use this Brand identity design plan?

It supports teams that need a finite delivery boundary and an explicit decision after Package brand guidelines.

How should I adapt the schedule?

Set dates and owners after creation, then add protected details such as Trademark filings and Final asset licenses.

Related templates

Templates

Use the Brand identity design template free

Keep scope, evidence, and ownership connected before the work moves forward.