Professional services Project timeline template

Agency website project

Best for delivering one client website through approved strategy, production, client validation, and launch handoff.

Best for delivering one client website through approved strategy, production, client validation, and launch handoff.

Put Run agency project kickoff and Agency website project complete on one agreed path.

Agency website project: make the path from Run agency project kickoff to Agency website project complete visible.

Agency website project: make the path from Run agency project kickoff to Agency website project complete visible.

This Agency website project template makes the client-facing path from Run agency project kickoff to Agency website project complete explicit. It keeps each working phase visible so the team can prepare decisions and handoffs before the next commitment is due.

The public starter remains intentionally clean. Add client files, commercial detail, credentials, and confidential evidence only after creating a private project.

Included schedule

16 rows, 10 links, already sequenced.

Explore the schedule to connect Run agency project kickoff and Agency website project complete.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
Week 5
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
19Day
20Day
21Day
22Day
23Day
24Day
25Day
Define website sitemap
Create content production plan
Create visual direction
Build page templates
Integrate approved content
Run staging review
Run client website validation

Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

Schedule details

Complete schedule table

Put Run agency project kickoff and Agency website project complete on one agreed path.

Work itemTypeScheduleDurationDepends on
Plan website delivery Phase Days 1–6 Derived rollup —
Run agency project kickoff Task Day 1 1 working day —
Define website sitemap Task Days 2–3 2 working days Run agency project kickoff
Create content production plan Task Days 4–5 2 working days Define website sitemap
Website brief approved Milestone Day 6 Milestone Create content production plan
Design and build Phase Days 7–20 Derived rollup —
Create visual direction Task Days 7–9 3 working days —
Build page templates Task Days 10–14 5 working days Create visual direction
Integrate approved content Task Days 15–17 3 working days Build page templates
Run staging review Task Days 18–19 2 working days Integrate approved content
Website ready for client validation Milestone Day 20 Milestone Run staging review
Validate and launch Phase Days 21–25 Derived rollup —
Run client website validation Task Days 21–22 2 working days —
Complete website launch Task Day 23 1 working day Run client website validation
Review launch handoff Task Day 24 1 working day Complete website launch
Agency website project complete Milestone Day 25 Milestone Review launch handoff

Who it helps

  • Teams delivering a defined agency website project
  • Project leads who need explicit ownership, decisions, and timing with a client

What is included

  • Plan website delivery: Run agency project kickoff → Define website sitemap → Create content production plan → Website brief approved.
  • Design and build: Create visual direction → Build page templates → Integrate approved content → Run staging review → Website ready for client validation.
  • Validate and launch: Run client website validation → Complete website launch → Review launch handoff → Agency website project complete.

Adapt after creation

  • This public planning aid contains no confidential client, contract, financial, or production material. Add protected details only inside your secured project.
  • Relative days show the order for Agency website project; set one real start date after creation.
  • Keep the Agency website project scope, owners, and decisions aligned before client commitments move forward.

How to use this template

Agency website project: make the path from Run agency project kickoff to Agency website project complete visible.

  1. 1

    Plan website delivery

    Sequence Run agency project kickoff → Define website sitemap → Create content production plan → Website brief approved so the next handoff is clear.

  2. 2

    Design and build

    Sequence Create visual direction → Build page templates → Integrate approved content → Run staging review → Website ready for client validation so the next handoff is clear.

  3. 3

    Validate and launch

    Sequence Run client website validation → Complete website launch → Review launch handoff → Agency website project complete so the next handoff is clear.

Not included

Planning aid

This public planning aid contains no confidential client, contract, financial, or production material. Add protected details only inside your secured project.

  • Agency contracts
  • Client analytics data
  • Client brand assets
  • Domain and DNS access
  • Production content
  • Website credentials

Template FAQ

Good to know

What does this Agency website project template include?

It sequences Plan website delivery, Design and build, Validate and launch around named work, dependencies, and decision points.

Who should use this Agency website project plan?

It supports a team completing one finite client engagement with a visible delivery boundary.

How should the schedule be adapted?

Set real dates and owners after creation, then add private client material only in the secured project.

Related templates

Templates

Use the Agency website project template free

Keep the Agency website project scope, owners, and decisions aligned before client commitments move forward.

Use the Agency website project template free

Put Run agency project kickoff and Agency website project complete on one agreed path.