Creative & media Project timeline template

Podcast Launch Timeline

Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.

Podcast launch: Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

Podcast launch: Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

Use the schedule to make creative review, release, and closeout handoffs visible. Show format: Define show concept, Set episode format and brand direction, Show format ready. Pilot production: Prepare pilot production plan, Record pilot episode, Edit pilot episode, Pilot release ready. Initial release: Prepare hosting setup, Prepare launch promotion, Release initial episodes, Run launch retrospective, Initial release and retrospective complete.

This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance. Not included: Unpublished audio assets, Hosting credentials.

Schedule

15 Rows, 9 Dependencies.

Podcast launch: Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

Read-only preview
Milestone
Week 1
Week 2
Week 3
Week 4
Week 5
1Day
2Day
3Day
4Day
5Day
6Day
7Day
8Day
9Day
10Day
11Day
12Day
13Day
14Day
15Day
16Day
17Day
18Day
19Day
20Day
21Day
Define show concept
Set episode format and brand direction
Prepare pilot production plan
Record pilot episode
Edit pilot episode
Prepare hosting setup
Prepare launch promotion
Release initial episodes
Run launch retrospective

Use the schedule to make creative review, release, and closeout handoffs visible.

Schedule

Schedule Rows

Podcast launch: Show format, Pilot production, Initial release.

Work itemTypeScheduleDurationDepends on
Show format Phase Days 1–5 Derived rollup —
Define show concept Task Days 1–2 2 working days —
Set episode format and brand direction Task Days 3–4 2 working days Define show concept
Show format ready Milestone Day 5 Milestone Set episode format and brand direction
Pilot production Phase Days 6–14 Derived rollup —
Prepare pilot production plan Task Days 6–7 2 working days —
Record pilot episode Task Days 8–10 3 working days Prepare pilot production plan
Edit pilot episode Task Days 11–13 3 working days Record pilot episode
Pilot release ready Milestone Day 14 Milestone Edit pilot episode
Initial release Phase Days 15–21 Derived rollup —
Prepare hosting setup Task Days 15–16 2 working days —
Prepare launch promotion Task Days 15–16 2 working days —
Release initial episodes Task Days 17–18 2 working days Prepare hosting setup, Prepare launch promotion
Run launch retrospective Task Days 19–20 2 working days Release initial episodes
Initial release and retrospective complete Milestone Day 21 Milestone Run launch retrospective

Event teams

  • Podcast launch — Creative teams
  • Creative project owners

Schedule

  • Show format: Define show concept, Set episode format and brand direction, Show format ready
  • Pilot production: Prepare pilot production plan, Record pilot episode, Edit pilot episode, Pilot release ready
  • Initial release: Prepare hosting setup, Prepare launch promotion, Release initial episodes, Run launch retrospective, Initial release and retrospective complete

Template guidance

  • Set real dates and accountable owners after creation.
  • Use this finite event plan to make the critical handoffs visible before delivery.
  • Not included: Unpublished audio assets, Hosting credentials.

Template guidance

Podcast launch: Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

  1. 1

    Show format

    Show format: Define show concept, Set episode format and brand direction, Show format ready.

  2. 2

    Pilot production

    Pilot production: Prepare pilot production plan, Record pilot episode, Edit pilot episode, Pilot release ready.

  3. 3

    Initial release

    Initial release: Prepare hosting setup, Prepare launch promotion, Release initial episodes, Run launch retrospective, Initial release and retrospective complete.

Not included

Good to know

This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.

  • Distribution accounts
  • Guest personal data
  • Hosting credentials
  • Rights records
  • Sponsorship contracts
  • Unpublished audio assets

Template FAQ

Good to know

What is included? Podcast launch

Schedule: Show format, Pilot production, Initial release.

Who is this for? Podcast launch

Creative teams — Creative project owners.

How should it be adapted? Podcast launch

Set real dates and accountable owners after creation. Not included: Unpublished audio assets, Hosting credentials.

Related templates

Related templates

Use this template free: Podcast launch

Set real dates and accountable owners after creation.

Use this template free: Podcast launch

This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.