# Webinar production

[Events & experiences](https://ganttfather.com/templates/#events-experiences) Project timeline template

# Webinar production

 Best for producing one live or recorded webinar from topic approval through rehearsal, broadcast, and follow-up.

 Best for producing one live or recorded webinar from topic approval through rehearsal, broadcast, and follow-up.

 [Use this template free: Webinar production](https://app.ganttfather.com/projects/new?template=webinar-production&entry=template-library)

 Use this finite event plan to make the critical handoffs visible before delivery.

## Webinar production: Use this finite event plan to make the critical handoffs visible before delivery.

 Best for producing one live or recorded webinar from topic approval through rehearsal, broadcast, and follow-up. The schedule moves through Webinar brief, Production and rehearsal and Broadcast and follow-up, making decisions, handoffs, and closeout visible before the event advances.

 After creating the project, set real dates and accountable owners. Use Define webinar topic, Confirm webinar speakers and Webinar brief approved as starting checkpoints, and keep Registrant personal data, Webinar platform credentials, Speaker agreements, Recording access, Payment details and Customer contact lists in the secured project.

 Schedule

## 14 Rows, 8 Dependencies.

 Schedule: Define webinar topic, Confirm webinar speakers, Webinar brief approved.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 Define webinar topic

 Confirm webinar speakers

 Create webinar run of show

 Open webinar registration

 Run technical rehearsal

 Publish webinar recording

 Send attendee follow-up

 Use this finite event plan to make the critical handoffs visible before delivery.

 Use this finite event plan to make the critical handoffs visible before delivery.

 Schedule

### Schedule Rows

 Webinar production: Use this finite event plan to make the critical handoffs visible before delivery.

 Work item Type Schedule Duration Depends on

 Webinar brief Phase Days 1–6 Derived rollup —

 Define webinar topic Task Days 1–2 2 working days —

 Confirm webinar speakers Task Days 3–5 3 working days Define webinar topic

 Webinar brief approved Milestone Day 6 Milestone Confirm webinar speakers

 Production and rehearsal Phase Days 7–12 Derived rollup —

 Create webinar run of show Task Days 7–9 3 working days —

 Open webinar registration Task Days 7–10 4 working days —

 Run technical rehearsal Task Days 10–11 2 working days Open webinar registration, Create webinar run of show

 Webinar ready to broadcast Milestone Day 12 Milestone Run technical rehearsal

 Broadcast and follow-up Phase Days 13–19 Derived rollup —

 Deliver webinar broadcast Task Day 13 1 working day —

 Publish webinar recording Task Days 14–15 2 working days Deliver webinar broadcast

 Send attendee follow-up Task Days 16–18 3 working days Publish webinar recording

 Webinar follow-up complete Milestone Day 19 Milestone Send attendee follow-up

## Event teams

- Event teams: Webinar production
- Event teams: Webinar brief, Production and rehearsal, Broadcast and follow-up

## Schedule

- Webinar brief: Define webinar topic, Confirm webinar speakers and Webinar brief approved
- Production and rehearsal: Create webinar run of show, Open webinar registration, Run technical rehearsal and Webinar ready to broadcast
- Broadcast and follow-up: Deliver webinar broadcast, Publish webinar recording, Send attendee follow-up and Webinar follow-up complete

## Template guidance

- Set the real event date, accountable owners, and decision deadlines after creation.
- Use Define webinar topic, Confirm webinar speakers and Webinar brief approved as starting checkpoints, then add venue- and team-specific work.
- Keep Registrant personal data, Webinar platform credentials, Speaker agreements, Recording access, Payment details and Customer contact lists in the secured project instead of this public planning template.

 Planning guidance

## Webinar production: Use this finite event plan to make the critical handoffs visible before delivery.

- 1

### Webinar brief

 Use Webinar brief to make the next decision and handoff visible before event work moves forward.

- 2

### Production and rehearsal

 Use Production and rehearsal to make the next decision and handoff visible before event work moves forward.

- 3

### Broadcast and follow-up

 Use Broadcast and follow-up to make the next decision and handoff visible before event work moves forward.

 Keep private details in your project

## Good to know

 This public template for Webinar production organizes a bounded schedule; it does not store operational records or private event data. Keep Registrant personal data, Webinar platform credentials, Speaker agreements, Recording access, Payment details and Customer contact lists in the secured project.

- Customer contact lists
- Payment details
- Recording access
- Registrant personal data
- Speaker agreements
- Webinar platform credentials

 Template FAQ

## Good to know

 What does the Webinar production template include? + It organizes Webinar brief, Production and rehearsal and Broadcast and follow-up into a finite schedule with named work, dependencies, and decision points.

 Who should use the Webinar production template? + Event teams: Webinar production. Event teams: Webinar brief, Production and rehearsal, Broadcast and follow-up.

 How should I adapt the Webinar production template? + Set real dates and owners, add event-specific work, and keep Registrant personal data, Webinar platform credentials, Speaker agreements, Recording access, Payment details and Customer contact lists in the secured project.

 Related templates

## Related templates

 [Related templates →](https://ganttfather.com/templates/)

 [Events & experiences 23 working days Wedding planning Best for planning one wedding from venue and vendor decisions through ceremony readiness and closeout.](https://ganttfather.com/templates/wedding-planning/)[Events & experiences 22 working days Trade show planning Best for preparing one exhibitor presence with booth, logistics, staffing, promotion, and lead handoff.](https://ganttfather.com/templates/trade-show-planning/)

 ![](https://ganttfather.com/logo.png)

## Use this template free

 Set the real event date, accountable owners, and decision deadlines after creation.

 [Use this template free: Webinar production](https://app.ganttfather.com/projects/new?template=webinar-production&entry=template-library) Use this finite event plan to make the critical handoffs visible before delivery.