# Vendor selection and onboarding template

[Business operations](https://ganttfather.com/templates/#business-operations) Project timeline template

# Vendor selection and onboarding template

 Plan one vendor selection and onboarding with clear owners, dependencies, approvals, and a finite completion point.

 Best for selecting and activating one vendor for a defined operating need.

 [Use the Vendor selection and onboarding template free](https://app.ganttfather.com/projects/new?template=vendor-selection-onboarding&entry=template-library)

 Keep Confirm vendor requirements, Research qualified vendors, and Evaluate vendor options connected so the next decision has clear evidence.

## Vendor selection and onboarding: make every decision and handoff visible.

 The Vendor selection and onboarding template gives operations teams a shared sequence through Select a vendor, Prepare activation, Onboard the vendor rather than a generic checklist.

 It connects Confirm vendor requirements, Research qualified vendors, Evaluate vendor options to the decisions that release the next stage, so responsibilities stay visible when work changes hands.

 After creating the project, set real dates and owners and add the protected organizational detail your team needs.

 Included schedule

## 13 rows and 7 dependencies, already sequenced.

 Keep Confirm vendor requirements, Research qualified vendors, and Evaluate vendor options connected so the next decision has clear evidence.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 Confirm vendor requirements

 Research qualified vendors

 Evaluate vendor options

 Complete vendor due diligence

 Prepare commercial inputs

 Set up vendor service

 Complete service handoff

 Replace relative working days with the real start date and assign an accountable owner to every row.

 Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

 Schedule details

### Complete schedule table

 Keep Confirm vendor requirements, Research qualified vendors, and Evaluate vendor options connected so the next decision has clear evidence.

 Work item Type Schedule Duration Depends on

 Select a vendor Phase Days 1–9 Derived rollup —

 Confirm vendor requirements Task Days 1–2 2 working days —

 Research qualified vendors Task Days 3–5 3 working days Confirm vendor requirements

 Evaluate vendor options Task Days 6–8 3 working days Research qualified vendors

 Vendor selection decision Milestone Day 9 Milestone Evaluate vendor options

 Prepare activation Phase Days 10–13 Derived rollup —

 Complete vendor due diligence Task Days 10–12 3 working days —

 Prepare commercial inputs Task Days 10–12 3 working days —

 Activation inputs ready Milestone Day 13 Milestone Prepare commercial inputs, Complete vendor due diligence

 Onboard the vendor Phase Days 14–19 Derived rollup —

 Set up vendor service Task Days 14–16 3 working days —

 Complete service handoff Task Days 17–18 2 working days Set up vendor service

 Vendor ready to operate Milestone Day 19 Milestone Complete service handoff

## Who it helps

- Operations leaders completing one vendor selection and onboarding
- Cross-functional teams coordinating approvals and handoffs

## What is included

- Select a vendor: Confirm vendor requirements, Research qualified vendors
- Prepare activation: Research qualified vendors, Evaluate vendor options
- Onboard the vendor: Evaluate vendor options

## Adapt after creation

- Set real dates and owners after creation, then add secured operating detail such as Vendor commercial pricing.
- Replace relative working days with a real start date and assign one accountable owner to every row.
- Keep Confirm vendor requirements, Research qualified vendors, and Evaluate vendor options connected so the next decision has clear evidence.

 How to use this template

## Keep Confirm vendor requirements, Research qualified vendors, and Evaluate vendor options connected so the next decision has clear evidence.

- 1

### Select a vendor

 Use Select a vendor to sequence Confirm vendor requirements, Research qualified vendors before releasing the next handoff.

- 2

### Prepare activation

 Use Prepare activation to sequence Research qualified vendors, Evaluate vendor options before releasing the next handoff.

- 3

### Onboard the vendor

 Use Onboard the vendor to sequence Evaluate vendor options before releasing the next handoff.

 Not included

## Planning aid

 This public planning aid contains no live access or private operating data. Add Vendor commercial pricing only inside your secured project.

- Contract negotiation terms
- System access credentials
- Vendor commercial pricing

 Template FAQ

## Good to know

 What does the Vendor selection and onboarding template include? + It turns Select a vendor, Prepare activation, Onboard the vendor into a practical schedule with named work, dependencies, and decision points.

 Who should use the Vendor selection and onboarding template? + Operations leaders completing one vendor selection and onboarding. Cross-functional teams coordinating approvals and handoffs

 How should I adapt the Vendor selection and onboarding plan? + Set real dates and owners after creation, then add secured operating detail such as Vendor commercial pricing.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Business operations 19 working days Business process improvement template Plan one business process improvement with clear owners, dependencies, approvals, and a finite completion point.](https://ganttfather.com/templates/business-process-improvement/)[Business operations 20 working days Office relocation template Plan one office relocation with clear owners, dependencies, approvals, and a finite completion point.](https://ganttfather.com/templates/office-relocation/)

 ![](https://ganttfather.com/logo.png)

## Use the Vendor selection and onboarding template free

 Keep Confirm vendor requirements, Research qualified vendors, and Evaluate vendor options connected so the next decision has clear evidence.

 [Use the Vendor selection and onboarding template free](https://app.ganttfather.com/projects/new?template=vendor-selection-onboarding&entry=template-library) Keep Confirm vendor requirements, Research qualified vendors, and Evaluate vendor options connected so the next decision has clear evidence.