# UX research

[Product & design](https://ganttfather.com/templates/#product-design) Project timeline template

# UX research

 Best for coordinating a bounded UX research project from Define research questions through Deliver product recommendations.

 Best for running one bounded UX study from research questions through synthesized findings and recommendations.

 [Use the UX research template free](https://app.ganttfather.com/projects/new?template=ux-research&entry=template-library)

 Put Define research questions, Run research sessions, and Deliver product recommendations on one agreed path.

## UX research: make the handoff from Define research questions to Deliver product recommendations visible.

 The UX research template turns a finite product-design outcome into a visible path through Prepare, Conduct, and Deliver. It gives a multidisciplinary team a shared sequence rather than a collection of disconnected workshops or tickets.

 The schedule connects Define research questions, Run research sessions, and Deliver product recommendations. Milestones such as Research study ready, Research insights approved, and Research findings delivered make the evidence or approval required for the next handoff easy to find.

 After creating the project, replace relative days with real dates, assign accountable owners, and add internal details only where they belong. The public starter deliberately excludes Participant identities and Raw session recordings.

 Included schedule

## 11 rows, 5 links, already sequenced.

 Explore the UX research schedule to connect Define research questions, Run research sessions, and Deliver product recommendations.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 Define research questions

 Recruit study participants

 Run research sessions

 Synthesize study evidence

 Deliver product recommendations

 Relative days show the order for UX research; set one real start date after creation.

 Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

 Schedule details

### Complete schedule table

 Put Define research questions, Run research sessions, and Deliver product recommendations on one agreed path.

 Work item Type Schedule Duration Depends on

 Prepare Phase Days 1–6 Derived rollup —

 Define research questions Task Days 1–2 2 working days —

 Recruit study participants Task Days 3–5 3 working days Define research questions

 Research study ready Milestone Day 6 Milestone Recruit study participants

 Conduct Phase Days 7–15 Derived rollup —

 Run research sessions Task Days 7–11 5 working days —

 Synthesize study evidence Task Days 12–14 3 working days Run research sessions

 Research insights approved Milestone Day 15 Milestone Synthesize study evidence

 Deliver Phase Days 16–18 Derived rollup —

 Deliver product recommendations Task Days 16–17 2 working days —

 Research findings delivered Milestone Day 18 Milestone Deliver product recommendations

## Who it helps

- Product managers and design leads responsible for UX research
- Researchers, designers, and delivery partners aligning the Deliver product recommendations decision

## What is included

- Prepare: Define research questions, Recruit study participants, and Research study ready
- Conduct: Run research sessions, Synthesize study evidence, and Research insights approved
- Deliver: Deliver product recommendations and Research findings delivered

## Adapt after creation

- Add secured information represented by Participant identities and Raw session recordings.
- Replace relative working days with the real project start date.
- Assign one accountable owner to each handoff and approval.

 How to use this template

## UX research: make the handoff from Define research questions to Deliver product recommendations visible.

- 1

### Prepare

 Start with Define research questions and Recruit study participants so the opening handoff is explicit.

- 2

### Conduct

 Use Run research sessions and Synthesize study evidence to turn progress into a concrete approval.

- 3

### Deliver

 Finish with Deliver product recommendations and record Research findings delivered for the next accountable team.

 Not included

## Planning aid

 This public planning aid contains no confidential research, contract, or production material. Add Participant identities and Raw session recordings only inside your secured project.

- Participant identities
- Raw session recordings

 Template FAQ

## Good to know

 What does the UX research template include? + It sequences Prepare, Conduct, and Deliver around named work such as Define research questions, Run research sessions, and Deliver product recommendations.

 Who should use this UX research plan? + It supports teams that need a finite delivery boundary and an explicit decision after Deliver product recommendations.

 How should I adapt the schedule? + Set dates and owners after creation, then add protected details such as Participant identities and Raw session recordings.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Product & design 18 working days Product discovery sprint Best for coordinating a bounded Product discovery sprint project from Frame product opportunity through Choose product direction.](https://ganttfather.com/templates/product-discovery-sprint/)[Product & design 20 working days Brand identity design Best for coordinating a bounded Brand identity design project from Align brand brief through Package brand guidelines.](https://ganttfather.com/templates/brand-identity-design/)

 ![](https://ganttfather.com/logo.png)

## Use the UX research template free

 Keep scope, evidence, and ownership connected before the work moves forward.

 [Use the UX research template free](https://app.ganttfather.com/projects/new?template=ux-research&entry=template-library) Put Define research questions, Run research sessions, and Deliver product recommendations on one agreed path.