# RFP response

[Sales & customer success](https://ganttfather.com/templates/#sales-customer-success) Project timeline template

# RFP response

 Best for producing one compliant request-for-proposal response through qualification, drafting, approval, and submission.

 Best for producing one compliant request-for-proposal response through qualification, drafting, approval, and submission.

 [Use the RFP response template free](https://app.ganttfather.com/projects/new?template=rfp-response&entry=template-library)

 Put Review RFP requirements and Response submitted on one agreed path.

## RFP response: make the handoff from Review RFP requirements to Response submitted visible.

# RFP response

 Use this RFP response template to make the path from Review RFP requirements to Response submitted visible. The schedule gives the team a shared sequence and keeps Bid decision confirmed, Response ready for approval, Response submitted easy to find.

## RFP response: make the handoff from Review RFP requirements to Response submitted visible.

 Best for producing one compliant request-for-proposal response through qualification, drafting, approval, and submission.

### Qualify opportunity

 Review RFP requirements ? Make bid decision ? Bid decision confirmed

### Develop response

 Assign response owners ? Draft technical response ? Draft commercial response ? Run response review ? Response ready for approval

### Approve & submit

 Finalize proposal response ? Approve final response ? Submit RFP response ? Response submitted

 Included schedule

## 15 rows, 10 links, already sequenced.

 Explore the schedule to connect Review RFP requirements and Response submitted.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 Review RFP requirements

 Draft commercial response

 Draft technical response

 Run response review

 Finalize proposal response

 Relative days show the order for RFP response; set one real start date after creation.

 Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

 Schedule details

### Complete schedule table

 Put Review RFP requirements and Response submitted on one agreed path.

 Work item Type Schedule Duration Depends on

 Qualify opportunity Phase Days 1–4 Derived rollup —

 Review RFP requirements Task Days 1–2 2 working days —

 Make bid decision Task Day 3 1 working day Review RFP requirements

 Bid decision confirmed Milestone Day 4 Milestone Make bid decision

 Develop response Phase Days 5–12 Derived rollup —

 Assign response owners Task Day 5 1 working day —

 Draft commercial response Task Days 6–9 4 working days Assign response owners

 Draft technical response Task Days 6–9 4 working days Assign response owners

 Run response review Task Days 10–11 2 working days Draft commercial response, Draft technical response

 Response ready for approval Milestone Day 12 Milestone Run response review

 Approve & submit Phase Days 13–17 Derived rollup —

 Finalize proposal response Task Days 13–14 2 working days —

 Approve final response Task Day 15 1 working day Finalize proposal response

 Submit RFP response Task Day 16 1 working day Approve final response

 Response submitted Milestone Day 17 Milestone Submit RFP response

## Who it helps

- Teams responsible for RFP response
- Leaders who need explicit ownership, decisions, and timing across customer-facing work

## What is included

- Qualify opportunity: Review RFP requirements, Make bid decision, Bid decision confirmed.
- Develop response: Assign response owners, Draft technical response, Draft commercial response, Run response review, Response ready for approval.
- Approve & submit: Finalize proposal response, Approve final response, Submit RFP response, Response submitted.

## Adapt after creation

- Add protected details such as Customer requirements, Bid pricing, Legal response documents, Proprietary attachments.
- Replace relative working days with the real project start date.
- Assign one accountable owner to each handoff and approval.

 How to use this template

## RFP response: make the handoff from Review RFP requirements to Response submitted visible.

- 1

### Qualify opportunity

 Sequence Review RFP requirements, Make bid decision, Bid decision confirmed so the next handoff is clear.

- 2

### Develop response

 Sequence Assign response owners, Draft technical response, Draft commercial response, Run response review, Response ready for approval so the next handoff is clear.

- 3

### Approve & submit

 Sequence Finalize proposal response, Approve final response, Submit RFP response, Response submitted so the next handoff is clear.

 Not included

## Planning aid

 This public planning aid contains no confidential customer, contract, or production material. Add Customer requirements, Bid pricing, Legal response documents, Proprietary attachments only inside your secured project.

- Bid pricing
- Customer requirements
- Legal response documents
- Proprietary attachments

 Template FAQ

## Good to know

 What does the RFP response template include? + It sequences Qualify opportunity, Develop response, Approve & submit around named work, dependencies, and decision points.

 Who should use this RFP response plan? + It supports teams responsible for rfp response that need a finite and visible delivery boundary.

 How should the schedule be adapted? + Set real dates and owners after creation, then add protected details such as Customer requirements, Bid pricing, Legal response documents, Proprietary attachments.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Sales & customer success 19 working days Customer onboarding Best for activating one newly contracted customer from sales handoff through an agreed onboarding-complete decision.](https://ganttfather.com/templates/customer-onboarding/)[Sales & customer success 16 working days Sales territory planning Best for defining account and geographic coverage for one named sales planning period through approved territory assignments.](https://ganttfather.com/templates/sales-territory-planning/)

 ![](https://ganttfather.com/logo.png)

## Use the RFP response template free

 Keep the RFP response scope, owners, and progress aligned before commitments move forward.

 [Use the RFP response template free](https://app.ganttfather.com/projects/new?template=rfp-response&entry=template-library) Put Review RFP requirements and Response submitted on one agreed path.