# Research study

[Research](https://ganttfather.com/templates/#research) Project timeline template

# Research study

 Best for running one bounded research study from a defined question through evidence, findings, and records closeout.

 Best for running one bounded research study from a defined question through evidence, findings, and records closeout.

 [Use this template free: Research study](https://app.ganttfather.com/projects/new?template=research-study&entry=template-library)

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

## Research study: How to use this template.

## Research study: How to use this template.

 Best for running one bounded research study from a defined question through evidence, findings, and records closeout.

### Study design

 Define research question, Draft study protocol, Research question and protocol recorded

### Collect evidence

 Prepare data collection plan, Gather study data, Review data quality, Collection complete

### Analyze and interpret

 Analyze findings, Interpret results, Finalize study records, Findings and study records finalized

 Adapt after creation

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

 Schedule

## 14 Rows, 8 Dependencies.

 Research study: Best for running one bounded research study from a defined question through evidence, findings, and records closeout.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 Week 6

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 22 Day

 23 Day

 24 Day

 25 Day

 26 Day

 Define research question

 Draft study protocol

 Prepare data collection plan

 Gather study data

 Review data quality

 Analyze findings

 Interpret results

 Finalize study records

 Relative working days show planned order, not calendar dates.

 Use the interactive schedule to inspect the planned sequence.

 Schedule details

### Schedule details

 Study design, Collect evidence, Analyze and interpret

 Work item Type Schedule Duration Depends on

 Study design Phase Days 1–6 Derived rollup —

 Define research question Task Days 1–2 2 working days —

 Draft study protocol Task Days 3–5 3 working days Define research question

 Research question and protocol recorded Milestone Day 6 Milestone Draft study protocol

 Collect evidence Phase Days 7–16 Derived rollup —

 Prepare data collection plan Task Days 7–8 2 working days —

 Gather study data Task Days 9–13 5 working days Prepare data collection plan

 Review data quality Task Days 14–15 2 working days Gather study data

 Collection complete Milestone Day 16 Milestone Review data quality

 Analyze and interpret Phase Days 17–26 Derived rollup —

 Analyze findings Task Days 17–20 4 working days —

 Interpret results Task Days 21–22 2 working days Analyze findings

 Finalize study records Task Days 23–25 3 working days Interpret results

 Findings and study records finalized Milestone Day 26 Milestone Finalize study records

## Who this helps

- Who this helps
- Research Planning team

## What is included

- Study design: Define research question → Research question and protocol recorded
- Collect evidence: Prepare data collection plan → Collection complete
- Analyze and interpret: Analyze findings → Findings and study records finalized

## Adapt after creation

- Relative working days show planned order, not calendar dates.
- Not included: Participant identifiers, Raw study data.

 How to use this template

## Research study: How to use this template

- 1

### Study design

 Define research question, Draft study protocol, Research question and protocol recorded

- 2

### Collect evidence

 Prepare data collection plan, Gather study data, Review data quality, Collection complete

- 3

### Analyze and interpret

 Analyze findings, Interpret results, Finalize study records, Findings and study records finalized

 Not included

## Planning boundary

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

- Consent records
- Ethics review documents
- Participant identifiers
- Private analysis notes
- Raw study data
- Research access credentials

 Frequently asked questions

## Good to know

 Research study: Frequently asked questions + What is included: Study design, Collect evidence, Analyze and interpret.

 Good to know + This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Research 17 working days Grant proposal Best for developing one grant proposal from a selected opportunity through internal review and a documented submission or withdrawal.](https://ganttfather.com/templates/grant-proposal/)[Research 25 working days Literature review Best for completing one scoped literature review through protocol, search, screening, synthesis, and a reviewed final artifact.](https://ganttfather.com/templates/literature-review/)

 ![](https://ganttfather.com/logo.png)

## Ready to adapt this plan?

 Relative working days show planned order, not calendar dates.

 [Use this template free: Research study](https://app.ganttfather.com/projects/new?template=research-study&entry=template-library) This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.