# Research publication

[Research](https://ganttfather.com/templates/#research) Project timeline template

# Research publication

 Best for taking one completed research manuscript through publication planning, review, submission, and a documented finite decision cycle.

 Best for taking one completed research manuscript through publication planning, review, submission, and a documented finite decision cycle.

 [Use this template free: Research publication](https://app.ganttfather.com/projects/new?template=research-publication&entry=template-library)

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

## Research publication: How to use this template.

## Research publication: How to use this template.

 Best for taking one completed research manuscript through publication planning, review, submission, and a documented finite decision cycle.

### Publication plan

 Select target publication, Map author and submission requirements, Publication plan recorded

### Draft and review

 Prepare manuscript draft, Run internal manuscript review, Prepare submission package, Submission package ready

### Submit and decide

 Submit manuscript, Review editorial outcome, Record revision or closeout decision, Submission cycle closed

 Adapt after creation

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

 Schedule

## 14 Rows, 8 Dependencies.

 Research publication: Best for taking one completed research manuscript through publication planning, review, submission, and a documented finite decision cycle.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 22 Day

 23 Day

 24 Day

 25 Day

 Select target publication

 Map author and submission requirements

 Prepare manuscript draft

 Run internal manuscript review

 Prepare submission package

 Review editorial outcome

 Record revision or closeout decision

 Relative working days show planned order, not calendar dates.

 Use the interactive schedule to inspect the planned sequence.

 Schedule details

### Schedule details

 Publication plan, Draft and review, Submit and decide

 Work item Type Schedule Duration Depends on

 Publication plan Phase Days 1–5 Derived rollup —

 Select target publication Task Days 1–2 2 working days —

 Map author and submission requirements Task Days 3–4 2 working days Select target publication

 Publication plan recorded Milestone Day 5 Milestone Map author and submission requirements

 Draft and review Phase Days 6–16 Derived rollup —

 Prepare manuscript draft Task Days 6–10 5 working days —

 Run internal manuscript review Task Days 11–13 3 working days Prepare manuscript draft

 Prepare submission package Task Days 14–15 2 working days Run internal manuscript review

 Submission package ready Milestone Day 16 Milestone Prepare submission package

 Submit and decide Phase Days 17–25 Derived rollup —

 Submit manuscript Task Day 17 1 working day —

 Review editorial outcome Task Days 18–22 5 working days Submit manuscript

 Record revision or closeout decision Task Days 23–24 2 working days Review editorial outcome

 Submission cycle closed Milestone Day 25 Milestone Record revision or closeout decision

## Who this helps

- Who this helps
- Research Planning team

## What is included

- Publication plan: Select target publication → Publication plan recorded
- Draft and review: Prepare manuscript draft → Submission package ready
- Submit and decide: Submit manuscript → Submission cycle closed

## Adapt after creation

- Relative working days show planned order, not calendar dates.
- Not included: Author contact details, Journal portal credentials.

 How to use this template

## Research publication: How to use this template

- 1

### Publication plan

 Select target publication, Map author and submission requirements, Publication plan recorded

- 2

### Draft and review

 Prepare manuscript draft, Run internal manuscript review, Prepare submission package, Submission package ready

- 3

### Submit and decide

 Submit manuscript, Review editorial outcome, Record revision or closeout decision, Submission cycle closed

 Not included

## Planning boundary

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

- Author contact details
- Journal portal credentials
- Publication agreement details
- Raw research data
- Reviewer correspondence
- Unpublished manuscript files

 Frequently asked questions

## Good to know

 Research publication: Frequently asked questions + What is included: Publication plan, Draft and review, Submit and decide.

 Good to know + This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Research 25 working days Literature review Best for completing one scoped literature review through protocol, search, screening, synthesis, and a reviewed final artifact.](https://ganttfather.com/templates/literature-review/)[Research 27 working days Thesis and dissertation Best for planning one thesis or dissertation from an approved proposal through research, drafting, review-ready work, and submission.](https://ganttfather.com/templates/thesis-dissertation/)

 ![](https://ganttfather.com/logo.png)

## Ready to adapt this plan?

 Relative working days show planned order, not calendar dates.

 [Use this template free: Research publication](https://app.ganttfather.com/projects/new?template=research-publication&entry=template-library) This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.