# Podcast Launch Timeline Template

[Creative & media](https://ganttfather.com/templates/#creative-media) Project timeline template

# Podcast Launch Timeline

 Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

 Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

 [Use this template free: Podcast launch](https://app.ganttfather.com/projects/new?template=podcast-launch&entry=template-library)

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.

## Podcast launch: Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

## Podcast launch: Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

 Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

 Use the schedule to make creative review, release, and closeout handoffs visible. Show format: Define show concept, Set episode format and brand direction, Show format ready. Pilot production: Prepare pilot production plan, Record pilot episode, Edit pilot episode, Pilot release ready. Initial release: Prepare hosting setup, Prepare launch promotion, Release initial episodes, Run launch retrospective, Initial release and retrospective complete.

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance. Not included: Unpublished audio assets, Hosting credentials.

 Schedule

## 15 Rows, 9 Dependencies.

 Podcast launch: Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 Define show concept

 Set episode format and brand direction

 Prepare pilot production plan

 Record pilot episode

 Edit pilot episode

 Prepare hosting setup

 Prepare launch promotion

 Release initial episodes

 Run launch retrospective

 Use this finite event plan to make the critical handoffs visible before delivery.

 Use the schedule to make creative review, release, and closeout handoffs visible.

 Schedule

### Schedule Rows

 Podcast launch: Show format, Pilot production, Initial release.

 Work item Type Schedule Duration Depends on

 Show format Phase Days 1–5 Derived rollup —

 Define show concept Task Days 1–2 2 working days —

 Set episode format and brand direction Task Days 3–4 2 working days Define show concept

 Show format ready Milestone Day 5 Milestone Set episode format and brand direction

 Pilot production Phase Days 6–14 Derived rollup —

 Prepare pilot production plan Task Days 6–7 2 working days —

 Record pilot episode Task Days 8–10 3 working days Prepare pilot production plan

 Edit pilot episode Task Days 11–13 3 working days Record pilot episode

 Pilot release ready Milestone Day 14 Milestone Edit pilot episode

 Initial release Phase Days 15–21 Derived rollup —

 Prepare hosting setup Task Days 15–16 2 working days —

 Prepare launch promotion Task Days 15–16 2 working days —

 Release initial episodes Task Days 17–18 2 working days Prepare hosting setup, Prepare launch promotion

 Run launch retrospective Task Days 19–20 2 working days Release initial episodes

 Initial release and retrospective complete Milestone Day 21 Milestone Run launch retrospective

## Event teams

- Podcast launch — Creative teams
- Creative project owners

## Schedule

- Show format: Define show concept, Set episode format and brand direction, Show format ready
- Pilot production: Prepare pilot production plan, Record pilot episode, Edit pilot episode, Pilot release ready
- Initial release: Prepare hosting setup, Prepare launch promotion, Release initial episodes, Run launch retrospective, Initial release and retrospective complete

## Template guidance

- Set real dates and accountable owners after creation.
- Use this finite event plan to make the critical handoffs visible before delivery.
- Not included: Unpublished audio assets, Hosting credentials.

 Template guidance

## Podcast launch: Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.

- 1

### Show format

 Show format: Define show concept, Set episode format and brand direction, Show format ready.

- 2

### Pilot production

 Pilot production: Prepare pilot production plan, Record pilot episode, Edit pilot episode, Pilot release ready.

- 3

### Initial release

 Initial release: Prepare hosting setup, Prepare launch promotion, Release initial episodes, Run launch retrospective, Initial release and retrospective complete.

 Not included

## Good to know

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.

- Distribution accounts
- Guest personal data
- Hosting credentials
- Rights records
- Sponsorship contracts
- Unpublished audio assets

 Template FAQ

## Good to know

 What is included? Podcast launch + Schedule: Show format, Pilot production, Initial release.

 Who is this for? Podcast launch + Creative teams — Creative project owners.

 How should it be adapted? Podcast launch + Set real dates and accountable owners after creation. Not included: Unpublished audio assets, Hosting credentials.

 Related templates

## Related templates

 [Related templates →](https://ganttfather.com/templates/)

 [Creative & media 27 working days Film Production Schedule Best for producing one film or bounded video work from a production brief through delivery of an approved final master.](https://ganttfather.com/templates/film-production/)[Creative & media 25 working days Editorial Calendar Project Plan Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone.](https://ganttfather.com/templates/editorial-calendar/)

 ![](https://ganttfather.com/logo.png)

## Use this template free: Podcast launch

 Set real dates and accountable owners after creation.

 [Use this template free: Podcast launch](https://app.ganttfather.com/projects/new?template=podcast-launch&entry=template-library) This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.