# New product development

[Product & design](https://ganttfather.com/templates/#product-design) Project timeline template

# New product development

 Best for coordinating a bounded New product development project from Define product scope through Prepare launch handoff.

 Best for taking one approved product concept through development, feasibility checks, and launch readiness.

 [Use the New product development template free](https://app.ganttfather.com/projects/new?template=new-product-development&entry=template-library)

 Put Define product scope, Build solution prototype, and Prepare launch handoff on one agreed path.

## New product development: make the handoff from Define product scope to Prepare launch handoff visible.

 The New product development template turns a finite product-design outcome into a visible path through Define, Develop, and Launch. It gives a multidisciplinary team a shared sequence rather than a collection of disconnected workshops or tickets.

 The schedule connects Define product scope, Build solution prototype, and Prepare launch handoff. Milestones such as Product concept approved, Development ready for launch, and Product launch ready make the evidence or approval required for the next handoff easy to find.

 After creating the project, replace relative days with real dates, assign accountable owners, and add internal details only where they belong. The public starter deliberately excludes Supplier contracts and Product costing.

 Included schedule

## 11 rows, 5 links, already sequenced.

 Explore the New product development schedule to connect Define product scope, Build solution prototype, and Prepare launch handoff.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 22 Day

 23 Day

 Define product scope

 Validate product concept

 Build solution prototype

 Test product feasibility

 Prepare launch handoff

 Relative days show the order for New product development; set one real start date after creation.

 Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

 Schedule details

### Complete schedule table

 Put Define product scope, Build solution prototype, and Prepare launch handoff on one agreed path.

 Work item Type Schedule Duration Depends on

 Define Phase Days 1–7 Derived rollup —

 Define product scope Task Days 1–3 3 working days —

 Validate product concept Task Days 4–6 3 working days Define product scope

 Product concept approved Milestone Day 7 Milestone Validate product concept

 Develop Phase Days 8–17 Derived rollup —

 Build solution prototype Task Days 8–12 5 working days —

 Test product feasibility Task Days 13–16 4 working days Build solution prototype

 Development ready for launch Milestone Day 17 Milestone Test product feasibility

 Launch Phase Days 18–23 Derived rollup —

 Prepare launch handoff Task Days 18–22 5 working days —

 Product launch ready Milestone Day 23 Milestone Prepare launch handoff

## Who it helps

- Product managers and design leads responsible for New product development
- Researchers, designers, and delivery partners aligning the Prepare launch handoff decision

## What is included

- Define: Define product scope, Validate product concept, and Product concept approved
- Develop: Build solution prototype, Test product feasibility, and Development ready for launch
- Launch: Prepare launch handoff and Product launch ready

## Adapt after creation

- Add secured information represented by Supplier contracts and Product costing.
- Replace relative working days with the real project start date.
- Assign one accountable owner to each handoff and approval.

 How to use this template

## New product development: make the handoff from Define product scope to Prepare launch handoff visible.

- 1

### Define

 Start with Define product scope and Validate product concept so the opening handoff is explicit.

- 2

### Develop

 Use Build solution prototype and Test product feasibility to turn progress into a concrete approval.

- 3

### Launch

 Finish with Prepare launch handoff and record Product launch ready for the next accountable team.

 Not included

## Planning aid

 This public planning aid contains no confidential research, contract, or production material. Add Supplier contracts and Product costing only inside your secured project.

- Product costing
- Supplier contracts

 Template FAQ

## Good to know

 What does the New product development template include? + It sequences Define, Develop, and Launch around named work such as Define product scope, Build solution prototype, and Prepare launch handoff.

 Who should use this New product development plan? + It supports teams that need a finite delivery boundary and an explicit decision after Prepare launch handoff.

 How should I adapt the schedule? + Set dates and owners after creation, then add protected details such as Supplier contracts and Product costing.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Product & design 18 working days Product discovery sprint Best for coordinating a bounded Product discovery sprint project from Frame product opportunity through Choose product direction.](https://ganttfather.com/templates/product-discovery-sprint/)[Product & design 23 working days Design system rollout Best for coordinating a bounded Design system rollout project from Audit interface inventory through Migrate target surfaces.](https://ganttfather.com/templates/design-system-rollout/)

 ![](https://ganttfather.com/logo.png)

## Use the New product development template free

 Keep scope, evidence, and ownership connected before the work moves forward.

 [Use the New product development template free](https://app.ganttfather.com/projects/new?template=new-product-development&entry=template-library) Put Define product scope, Build solution prototype, and Prepare launch handoff on one agreed path.