# Mobile app launch

[Software & technology](https://ganttfather.com/templates/#software-technology) Project timeline template

# Mobile app launch

 Best for preparing one mobile app release for store submission, publication, and launch checks.

 Best for preparing one mobile app release for store submission, publication, and launch checks.

 [Use the Mobile app launch template free](https://app.ganttfather.com/projects/new?template=mobile-app-launch&entry=template-library)

 Make the sequence from Release readiness, Store submission and Launch explicit before work starts. Keep Prepare release candidate, Prepare store build and Prepare launch communications connected instead of tracking them in separate documents.

## Mobile app launch: connect Release readiness to Launch without losing a handoff.

# Mobile app launch

 Mobile app launch makes Prepare release candidate, Prepare store build, and Mobile app live explicit checkpoints in one working plan. Best for preparing one mobile app release for store submission, publication, and launch checks.

## Execution path

 The sequence shows what must be ready between Prepare release candidate and Mobile app live, so the next owner can act on a defined decision rather than an assumed handoff.

### Release readiness

 Prepare release candidate → Prepare store assets → Release ready for submission

### Store submission

 Prepare store build → Finalize store listing → Store submission complete

### Launch

 Prepare launch communications → Publish mobile app → Monitor launch → Mobile app live

 Included schedule

## 13 rows, 7 links, already sequenced.

 Use this Mobile app launch plan to coordinate Prepare release candidate, Prepare store build and Prepare launch communications in one dependency-aware schedule.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 Prepare release candidate

 Prepare store assets

 Prepare store build

 Finalize store listing

 Prepare launch communications

 Monitor launch

 Replace relative days with the real start date and assign an accountable owner to every row.

 Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

 Schedule details

### Complete schedule table

 Make the sequence from Release readiness, Store submission and Launch explicit before work starts. Keep Prepare release candidate, Prepare store build and Prepare launch communications connected instead of tracking them in separate documents.

 Work item Type Schedule Duration Depends on

 Release readiness Phase Days 1–6 Derived rollup —

 Prepare release candidate Task Days 1–2 2 working days —

 Prepare store assets Task Days 3–5 3 working days Prepare release candidate

 Release ready for submission Milestone Day 6 Milestone Prepare store assets

 Store submission Phase Days 7–12 Derived rollup —

 Prepare store build Task Days 7–8 2 working days —

 Finalize store listing Task Days 9–11 3 working days Prepare store build

 Store submission complete Milestone Day 12 Milestone Finalize store listing

 Launch Phase Days 13–20 Derived rollup —

 Prepare launch communications Task Days 13–14 2 working days —

 Publish mobile app Task Day 15 1 working day Prepare launch communications

 Monitor launch Task Days 16–19 4 working days Publish mobile app

 Mobile app live Milestone Day 20 Milestone Monitor launch

## Who it helps

- Mobile product managers preparing store release
- Engineering, QA, and launch marketing leads

## What is included

- Release readiness: Prepare release candidate, Prepare store assets and Release ready for submission
- Store submission: Prepare store build, Finalize store listing and Store submission complete
- Launch: Prepare launch communications, Publish mobile app, Monitor launch and Mobile app live

## Adapt after creation

- Add the team-owned access, data, or operating details represented by Store account credentials and Signing certificates.
- Replace relative days with the real start date and assign an accountable owner to every row.
- Add review gates, rollback steps, or evidence required by your organization.

 How to use this template

## Make the sequence from Release readiness, Store submission and Launch explicit before work starts. Keep Prepare release candidate, Prepare store build and Prepare launch communications connected instead of tracking them in separate documents.

- 1

### Release readiness

 Move through Prepare release candidate, Prepare store assets and Release ready for submission while keeping the Release readiness handoff visible before the next stage begins.

- 2

### Store submission

 Move through Prepare store build, Finalize store listing and Store submission complete while keeping the Store submission handoff visible before the next stage begins.

- 3

### Launch

 Move through Prepare launch communications, Publish mobile app, Monitor launch and Mobile app live while keeping the Launch handoff visible before the next stage begins.

 Not included

## Planning aid

 This public planning aid contains no live access or production data. Add Store account credentials and Signing certificates only inside your secured project.

- Customer data
- Production analytics
- Push provider credentials
- Release assets
- Signing certificates
- Store account credentials

 Template FAQ

## Good to know

 What does the Mobile app launch template include? + It covers Release readiness, Store submission and Launch and sequences concrete work such as Prepare release candidate, Prepare store build and Prepare launch communications.

 Who should use the Mobile app launch template? + It is designed for Mobile product managers preparing store release and Engineering, QA, and launch marketing leads.

 How should I adapt the Mobile app launch plan? + Set real dates and owners after creation, then add operational details such as Store account credentials and Signing certificates; those are deliberately excluded from the public starter.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Software & technology 19 working days Software Release Timeline Plan a software release from scope through deployment with a practical 19-working-day schedule.](https://ganttfather.com/templates/software-release-timeline/)[Marketing & growth 20 working days Product launch campaign Best for coordinating the marketing campaign for one product release from launch narrative through the first readout.](https://ganttfather.com/templates/product-launch-campaign/)

 ![](https://ganttfather.com/logo.png)

## Use the Mobile app launch template free

 Make the sequence from Release readiness, Store submission and Launch explicit before work starts. Keep Prepare release candidate, Prepare store build and Prepare launch communications connected instead of tracking them in separate documents.

 [Use the Mobile app launch template free](https://app.ganttfather.com/projects/new?template=mobile-app-launch&entry=template-library) Make the sequence from Release readiness, Store submission and Launch explicit before work starts. Keep Prepare release candidate, Prepare store build and Prepare launch communications connected instead of tracking them in separate documents.