# Film Production Schedule Template

[Creative & media](https://ganttfather.com/templates/#creative-media) Project timeline template

# Film Production Schedule

 Best for producing one film or bounded video work from a production brief through delivery of an approved final master.

 Best for producing one film or bounded video work from a production brief through delivery of an approved final master.

 [Use this template free: Film production](https://app.ganttfather.com/projects/new?template=film-production&entry=template-library)

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.

## Film production: Best for producing one film or bounded video work from a production brief through delivery of an approved final master.

## Film production: Best for producing one film or bounded video work from a production brief through delivery of an approved final master.

 Best for producing one film or bounded video work from a production brief through delivery of an approved final master.

 Use the schedule to make creative review, release, and closeout handoffs visible. Preproduction: Confirm production brief, Create script and production breakdown, Preproduction plan ready. Production: Prepare principal photography schedule, Complete principal photography, Review captured footage, Production complete. Postproduction and delivery: Edit picture, Complete sound and color finish, Run final master review, Final master approved for delivery.

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance. Not included: Unpublished creative assets, Production credentials.

 Schedule

## 14 Rows, 8 Dependencies.

 Film production: Best for producing one film or bounded video work from a production brief through delivery of an approved final master.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 Week 6

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 22 Day

 23 Day

 24 Day

 25 Day

 26 Day

 27 Day

 28 Day

 Confirm production brief

 Create script and production breakdown

 Prepare principal photography schedule

 Complete principal photography

 Review captured footage

 Edit picture

 Complete sound and color finish

 Run final master review

 Use this finite event plan to make the critical handoffs visible before delivery.

 Use the schedule to make creative review, release, and closeout handoffs visible.

 Schedule

### Schedule Rows

 Film production: Preproduction, Production, Postproduction and delivery.

 Work item Type Schedule Duration Depends on

 Preproduction Phase Days 1–6 Derived rollup —

 Confirm production brief Task Days 1–2 2 working days —

 Create script and production breakdown Task Days 3–5 3 working days Confirm production brief

 Preproduction plan ready Milestone Day 6 Milestone Create script and production breakdown

 Production Phase Days 7–17 Derived rollup —

 Prepare principal photography schedule Task Days 7–8 2 working days —

 Complete principal photography Task Days 9–14 6 working days Prepare principal photography schedule

 Review captured footage Task Days 15–16 2 working days Complete principal photography

 Production complete Milestone Day 17 Milestone Review captured footage

 Postproduction and delivery Phase Days 18–28 Derived rollup —

 Edit picture Task Days 18–22 5 working days —

 Complete sound and color finish Task Days 23–25 3 working days Edit picture

 Run final master review Task Days 26–27 2 working days Complete sound and color finish

 Final master approved for delivery Milestone Day 28 Milestone Run final master review

## Event teams

- Film production — Creative teams
- Creative project owners

## Schedule

- Preproduction: Confirm production brief, Create script and production breakdown, Preproduction plan ready
- Production: Prepare principal photography schedule, Complete principal photography, Review captured footage, Production complete
- Postproduction and delivery: Edit picture, Complete sound and color finish, Run final master review, Final master approved for delivery

## Template guidance

- Set real dates and accountable owners after creation.
- Use this finite event plan to make the critical handoffs visible before delivery.
- Not included: Unpublished creative assets, Production credentials.

 Template guidance

## Film production: Best for producing one film or bounded video work from a production brief through delivery of an approved final master.

- 1

### Preproduction

 Preproduction: Confirm production brief, Create script and production breakdown, Preproduction plan ready.

- 2

### Production

 Production: Prepare principal photography schedule, Complete principal photography, Review captured footage, Production complete.

- 3

### Postproduction and delivery

 Postproduction and delivery: Edit picture, Complete sound and color finish, Run final master review, Final master approved for delivery.

 Not included

## Good to know

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.

- Distribution agreements
- Location contracts
- Production credentials
- Rights records
- Talent personal data
- Unpublished creative assets

 Template FAQ

## Good to know

 What is included? Film production + Schedule: Preproduction, Production, Postproduction and delivery.

 Who is this for? Film production + Creative teams — Creative project owners.

 How should it be adapted? Film production + Set real dates and accountable owners after creation. Not included: Unpublished creative assets, Production credentials.

 Related templates

## Related templates

 [Related templates →](https://ganttfather.com/templates/)

 [Creative & media 20 working days Podcast Launch Timeline Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.](https://ganttfather.com/templates/podcast-launch/)[Creative & media 32 working days Book Writing Project Plan Best for completing one book manuscript from concept and outline through drafting, editorial review, and a review-ready handoff.](https://ganttfather.com/templates/book-writing/)

 ![](https://ganttfather.com/logo.png)

## Use this template free: Film production

 Set real dates and accountable owners after creation.

 [Use this template free: Film production](https://app.ganttfather.com/projects/new?template=film-production&entry=template-library) This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.