title: "Editorial Calendar Project Plan Template"
description: "Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone."
canonical: "https://ganttfather.com/templates/editorial-calendar/"
locale: "en"
category: "product"
---

# Editorial Calendar Project Plan Template

[Creative & media](https://ganttfather.com/templates/#creative-media) Project timeline template

# Editorial Calendar Project Plan

 Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone.

 Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone.

 [Use this template free: Editorial calendar](https://app.ganttfather.com/projects/new?template=editorial-calendar&entry=template-library)

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.

## Editorial calendar: Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone.

## Editorial calendar: Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone.

 Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone.

 Use the schedule to make creative review, release, and closeout handoffs visible. Editorial period plan: Define editorial period goals, Map bounded content schedule, Editorial period calendar approved. Create planned content: Prepare planned content briefs, Create planned content set, Review planned content, Bounded content set ready. Publish and close period: Publish planned editorial period, Review editorial period results, Run editorial period retrospective, Bounded editorial period closed.

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance. Not included: Unpublished creative assets, Publishing credentials.

 Schedule

## 14 Rows, 8 Dependencies.

 Editorial calendar: Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 Week 6

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 22 Day

 23 Day

 24 Day

 25 Day

 26 Day

 Define editorial period goals

 Map bounded content schedule

 Prepare planned content briefs

 Create planned content set

 Review planned content

 Publish planned editorial period

 Review editorial period results

 Run editorial period retrospective

 Use this finite event plan to make the critical handoffs visible before delivery.

 Use the schedule to make creative review, release, and closeout handoffs visible.

 Schedule

### Schedule Rows

 Editorial calendar: Editorial period plan, Create planned content, Publish and close period.

 Work item Type Schedule Duration Depends on

 Editorial period plan Phase Days 1–6 Derived rollup —

 Define editorial period goals Task Days 1–2 2 working days —

 Map bounded content schedule Task Days 3–5 3 working days Define editorial period goals

 Editorial period calendar approved Milestone Day 6 Milestone Map bounded content schedule

 Create planned content Phase Days 7–17 Derived rollup —

 Prepare planned content briefs Task Days 7–8 2 working days —

 Create planned content set Task Days 9–14 6 working days Prepare planned content briefs

 Review planned content Task Days 15–16 2 working days Create planned content set

 Bounded content set ready Milestone Day 17 Milestone Review planned content

 Publish and close period Phase Days 18–26 Derived rollup —

 Publish planned editorial period Task Days 18–21 4 working days —

 Review editorial period results Task Days 22–23 2 working days Publish planned editorial period

 Run editorial period retrospective Task Days 24–25 2 working days Review editorial period results

 Bounded editorial period closed Milestone Day 26 Milestone Run editorial period retrospective

## Event teams

- Editorial calendar — Creative teams
- Creative project owners

## Schedule

- Editorial period plan: Define editorial period goals, Map bounded content schedule, Editorial period calendar approved
- Create planned content: Prepare planned content briefs, Create planned content set, Review planned content, Bounded content set ready
- Publish and close period: Publish planned editorial period, Review editorial period results, Run editorial period retrospective, Bounded editorial period closed

## Template guidance

- Set real dates and accountable owners after creation.
- Use this finite event plan to make the critical handoffs visible before delivery.
- Not included: Unpublished creative assets, Publishing credentials.

 Template guidance

## Editorial calendar: Best for planning and completing one bounded editorial period from content goals through published work, review, and a documented close milestone.

- 1

### Editorial period plan

 Editorial period plan: Define editorial period goals, Map bounded content schedule, Editorial period calendar approved.

- 2

### Create planned content

 Create planned content: Prepare planned content briefs, Create planned content set, Review planned content, Bounded content set ready.

- 3

### Publish and close period

 Publish and close period: Publish planned editorial period, Review editorial period results, Run editorial period retrospective, Bounded editorial period closed.

 Not included

## Good to know

 This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.

- Content contracts
- Contributor personal data
- Private performance data
- Publishing credentials
- Rights records
- Unpublished creative assets

 Template FAQ

## Good to know

 What is included? Editorial calendar + Schedule: Editorial period plan, Create planned content, Publish and close period.

 Who is this for? Editorial calendar + Creative teams — Creative project owners.

 How should it be adapted? Editorial calendar + Set real dates and accountable owners after creation. Not included: Unpublished creative assets, Publishing credentials.

 Related templates

## Related templates

 [Related templates →](https://ganttfather.com/templates/)

 [Creative & media 20 working days Podcast Launch Timeline Best for launching one podcast series from show concept through pilot production, initial release, and a launch retrospective.](https://ganttfather.com/templates/podcast-launch/)[Creative & media 22 working days YouTube Channel Launch Plan Best for launching one YouTube channel from approved concept through initial videos, publication, and a first release review.](https://ganttfather.com/templates/youtube-channel-launch/)

 ![](https://ganttfather.com/logo.png)

## Use this template free: Editorial calendar

 Set real dates and accountable owners after creation.

 [Use this template free: Editorial calendar](https://app.ganttfather.com/projects/new?template=editorial-calendar&entry=template-library) This is a planning aid, not a promise of distribution, audience growth, publishing, or legal clearance.