# Curriculum redesign

[Education](https://ganttfather.com/templates/#education) Project timeline template

# Curriculum redesign

 Best for completing one bounded curriculum redesign project with a visible sequence of decisions and handoffs.

 Best for revising one defined curriculum through evidence review, course mapping, and an implementation handoff.

 [Use this template free: Curriculum redesign](https://app.ganttfather.com/projects/new?template=curriculum-redesign&entry=template-library)

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

## Curriculum redesign: How to use this template.

## Curriculum redesign: How to use this template.

 Best for completing one bounded curriculum redesign project with a visible sequence of decisions and handoffs.

### Review curriculum evidence

 Review redesign evidence, Map revised learning outcomes, Redesign scope recorded

### Redesign curriculum package

 Create revised course map, Sequence curriculum changes, Prepare curriculum change summary, Curriculum package ready for review

### Review and hand off

 Run curriculum review, Prepare implementation handoff, Curriculum redesign handoff complete

 Adapt after creation

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

 Schedule

## 13 Rows, 8 Dependencies.

 Curriculum redesign: Best for completing one bounded curriculum redesign project with a visible sequence of decisions and handoffs.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 Review redesign evidence

 Map revised learning outcomes

 Create revised course map

 Prepare curriculum change summary

 Sequence curriculum changes

 Run curriculum review

 Prepare implementation handoff

 Relative working days show planned order, not calendar dates.

 Use the interactive schedule to inspect the planned sequence.

 Schedule details

### Schedule details

 Review curriculum evidence, Redesign curriculum package, Review and hand off

 Work item Type Schedule Duration Depends on

 Review curriculum evidence Phase Days 1–6 Derived rollup —

 Review redesign evidence Task Days 1–2 2 working days —

 Map revised learning outcomes Task Days 3–5 3 working days Review redesign evidence

 Redesign scope recorded Milestone Day 6 Milestone Map revised learning outcomes

 Redesign curriculum package Phase Days 7–13 Derived rollup —

 Create revised course map Task Days 7–9 3 working days —

 Prepare curriculum change summary Task Days 10–12 3 working days Create revised course map

 Sequence curriculum changes Task Days 10–11 2 working days Create revised course map

 Curriculum package ready for review Milestone Day 13 Milestone Prepare curriculum change summary, Sequence curriculum changes

 Review and hand off Phase Days 14–18 Derived rollup —

 Run curriculum review Task Days 14–15 2 working days —

 Prepare implementation handoff Task Days 16–17 2 working days Run curriculum review

 Curriculum redesign handoff complete Milestone Day 18 Milestone Prepare implementation handoff

## Who this helps

- Who this helps
- Education Planning team

## What is included

- Review curriculum evidence: Review redesign evidence → Redesign scope recorded
- Redesign curriculum package: Create revised course map → Curriculum package ready for review
- Review and hand off: Run curriculum review → Curriculum redesign handoff complete

## Adapt after creation

- Relative working days show planned order, not calendar dates.
- Not included: Student records, Private program evidence.

 How to use this template

## Curriculum redesign: How to use this template

- 1

### Review curriculum evidence

 Review redesign evidence, Map revised learning outcomes, Redesign scope recorded

- 2

### Redesign curriculum package

 Create revised course map, Sequence curriculum changes, Prepare curriculum change summary, Curriculum package ready for review

- 3

### Review and hand off

 Run curriculum review, Prepare implementation handoff, Curriculum redesign handoff complete

 Not included

## Planning boundary

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

- Committee records
- Licensed course materials
- Private program evidence
- Staff evaluation notes
- Student records

 Frequently asked questions

## Good to know

 Curriculum redesign: Frequently asked questions + What is included: Review curriculum evidence, Redesign curriculum package, Review and hand off.

 Good to know + This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Education 15 working days Course development Best for completing one bounded course development project with a visible sequence of decisions and handoffs.](https://ganttfather.com/templates/course-development/)[Education 15 working days Academic semester planning Best for completing one bounded academic semester planning project with a visible sequence of decisions and handoffs.](https://ganttfather.com/templates/academic-semester-planning/)

 ![](https://ganttfather.com/logo.png)

## Ready to adapt this plan?

 Relative working days show planned order, not calendar dates.

 [Use this template free: Curriculum redesign](https://app.ganttfather.com/projects/new?template=curriculum-redesign&entry=template-library) This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.