title: "Cloud migration"
description: "Best for moving a defined application or workload portfolio to an approved cloud target with cutover controls."
canonical: "https://ganttfather.com/templates/cloud-migration/"
locale: "en"
category: "product"
---

# Cloud migration

[Software & technology](https://ganttfather.com/templates/#software-technology) Project timeline template

# Cloud migration

 Best for moving a defined application or workload portfolio to an approved cloud target with cutover controls.

 Best for moving a defined application or workload portfolio to an approved cloud target with cutover controls.

 [Use the Cloud migration template free](https://app.ganttfather.com/projects/new?template=cloud-migration&entry=template-library)

 Make the sequence from Discovery, Migrate and Cutover explicit before work starts. Keep Inventory workloads, Prepare landing zone and Confirm cutover readiness connected instead of tracking them in separate documents.

## Cloud migration: connect Discovery to Cutover without losing a handoff.

# Cloud migration

 Cloud migration makes Inventory workloads, Prepare landing zone, and Migration complete explicit checkpoints in one working plan. Best for moving a defined application or workload portfolio to an approved cloud target with cutover controls.

## Execution path

 The sequence shows what must be ready between Inventory workloads and Migration complete, so the next owner can act on a defined decision rather than an assumed handoff.

### Discovery

 Inventory workloads → Design target environment → Migration approach approved

### Migrate

 Prepare landing zone → Migrate workloads → Validate migrated workloads → Ready for cutover

### Cutover

 Confirm cutover readiness → Switch production traffic → Verify cloud operation → Migration complete

 Included schedule

## 14 rows, 9 links, already sequenced.

 Use this Cloud migration plan to coordinate Inventory workloads, Prepare landing zone and Confirm cutover readiness in one dependency-aware schedule.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 Week 6

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 22 Day

 23 Day

 24 Day

 25 Day

 26 Day

 Inventory workloads

 Design target environment

 Prepare landing zone

 Migrate workloads

 Validate migrated workloads

 Confirm cutover readiness

 Switch production traffic

 Verify cloud operation

 Replace relative days with the real start date and assign an accountable owner to every row.

 Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

 Schedule details

### Complete schedule table

 Make the sequence from Discovery, Migrate and Cutover explicit before work starts. Keep Inventory workloads, Prepare landing zone and Confirm cutover readiness connected instead of tracking them in separate documents.

 Work item Type Schedule Duration Depends on

 Discovery Phase Days 1–7 Derived rollup —

 Inventory workloads Task Days 1–3 3 working days —

 Design target environment Task Days 4–6 3 working days Inventory workloads

 Migration approach approved Milestone Day 7 Milestone Design target environment

 Migrate Phase Days 8–18 Derived rollup —

 Prepare landing zone Task Days 8–11 4 working days —

 Migrate workloads Task Days 12–17 6 working days Prepare landing zone

 Validate migrated workloads Task Days 14–17 4 working days Prepare landing zone

 Ready for cutover Milestone Day 18 Milestone Validate migrated workloads, Migrate workloads

 Cutover Phase Days 19–26 Derived rollup —

 Confirm cutover readiness Task Days 19–20 2 working days —

 Switch production traffic Task Days 21–22 2 working days Confirm cutover readiness

 Verify cloud operation Task Days 23–25 3 working days Switch production traffic

 Migration complete Milestone Day 26 Milestone Verify cloud operation

## Who it helps

- Cloud program managers sequencing migration waves
- Platform, security, and operations leads planning cutover

## What is included

- Discovery: Inventory workloads, Design target environment and Migration approach approved
- Migrate: Prepare landing zone, Migrate workloads, Validate migrated workloads and Ready for cutover
- Cutover: Confirm cutover readiness, Switch production traffic, Verify cloud operation and Migration complete

## Adapt after creation

- Add the team-owned access, data, or operating details represented by Cloud console credentials and Production secrets.
- Replace relative days with the real start date and assign an accountable owner to every row.
- Add review gates, rollback steps, or evidence required by your organization.

 How to use this template

## Make the sequence from Discovery, Migrate and Cutover explicit before work starts. Keep Inventory workloads, Prepare landing zone and Confirm cutover readiness connected instead of tracking them in separate documents.

- 1

### Discovery

 Move through Inventory workloads, Design target environment and Migration approach approved while keeping the Discovery handoff visible before the next stage begins.

- 2

### Migrate

 Move through Prepare landing zone, Migrate workloads, Validate migrated workloads and Ready for cutover while keeping the Migrate handoff visible before the next stage begins.

- 3

### Cutover

 Move through Confirm cutover readiness, Switch production traffic, Verify cloud operation and Migration complete while keeping the Cutover handoff visible before the next stage begins.

 Not included

## Planning aid

 This public planning aid contains no live access or production data. Add Cloud console credentials and Production secrets only inside your secured project.

- Backup archives
- Cloud console credentials
- Customer data
- Network configurations
- Production secrets
- Vendor contracts

 Template FAQ

## Good to know

 What does the Cloud migration template include? + It covers Discovery, Migrate and Cutover and sequences concrete work such as Inventory workloads, Prepare landing zone and Confirm cutover readiness.

 Who should use the Cloud migration template? + It is designed for Cloud program managers sequencing migration waves and Platform, security, and operations leads planning cutover.

 How should I adapt the Cloud migration plan? + Set real dates and owners after creation, then add operational details such as Cloud console credentials and Production secrets; those are deliberately excluded from the public starter.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Sales & customer success 21 working days CRM implementation Best for implementing one CRM instance through approved scope, data preparation, configuration, testing, training, and adoption verification.](https://ganttfather.com/templates/crm-implementation/)[Software & technology 19 working days Software Release Timeline Plan a software release from scope through deployment with a practical 19-working-day schedule.](https://ganttfather.com/templates/software-release-timeline/)

 ![](https://ganttfather.com/logo.png)

## Use the Cloud migration template free

 Make the sequence from Discovery, Migrate and Cutover explicit before work starts. Keep Inventory workloads, Prepare landing zone and Confirm cutover readiness connected instead of tracking them in separate documents.

 [Use the Cloud migration template free](https://app.ganttfather.com/projects/new?template=cloud-migration&entry=template-library) Make the sequence from Discovery, Migrate and Cutover explicit before work starts. Keep Inventory workloads, Prepare landing zone and Confirm cutover readiness connected instead of tracking them in separate documents.