# Client Delivery Plan Template

[Professional services](https://ganttfather.com/templates/#professional-services) Project timeline template

# Client Delivery Plan

 Manage discovery, delivery, review, and handoff with a client-facing project timeline.

 Best for managing a client engagement from discovery through handoff.

 [Use this template free](https://app.ganttfather.com/projects/new?template=client-delivery&entry=template-library)

 Your first project is included. Existing accounts stay subject to their available project capacity.

## A client delivery plan that carries agreed work from discovery through approval and handoff.

 Use this client delivery plan template to make every handoff from kickoff through client approval easier to see. The schedule protects the sequence from requirements through approval, including room for review and revisions before the final handoff.

 It begins with a short discovery phase, turns agreed requirements into a delivery plan, and then gives the client review and revision cycle its own place in the schedule. That makes the approval path explicit instead of treating it as a final administrative step.

 The public template intentionally does not contain client data, contracts, invoices, or private files. Add those details only in the project you create for the engagement.

 Included schedule

## 14 rows, 9 links, already sequenced.

 A read-only preview of the published version. Click a bar, double-click it, or press Enter in the preview to inspect it.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 22 Day

 23 Day

 24 Day

 25 Day

 Gather requirements

 Create work plan

 Execute delivery

 Midpoint review

 Client review

 Apply revisions

 Handoff

 Day numbers are relative working days, not calendar dates. Set one start date and auto-scheduling resolves the rest.

 Read-only shared Gantt preview. Click or focus a bar and press Enter to inspect it.

 Schedule details

### Complete schedule table

 The same published schedule is available below as a semantic table for detailed review.

 Work item Type Schedule Duration Depends on

 Discovery Phase Days 1–5 Derived rollup —

 Project kickoff Milestone Day 1 Milestone —

 Gather requirements Task Days 2–4 3 working days Project kickoff

 Requirements approved Milestone Day 5 Milestone Gather requirements

 Delivery Phase Days 6–16 Derived rollup —

 Create work plan Task Days 6–7 2 working days —

 Execute delivery Task Days 8–15 8 working days Create work plan

 Midpoint review Task Days 12–13 2 working days Create work plan

 Delivery ready Milestone Day 16 Milestone Execute delivery, Midpoint review

 Acceptance Phase Days 17–25 Derived rollup —

 Client review Task Days 17–19 3 working days —

 Apply revisions Task Days 20–22 3 working days Client review

 Client approval Milestone Day 23 Milestone Apply revisions

 Handoff Task Days 24–25 2 working days Client approval

## Who it helps

- Client services teams managing agreed deliverables
- Project managers coordinating reviews and handoff

## What is included

- Kickoff and requirements approval
- Work planning, execution, and midpoint review
- Client review, revisions, approval, and handoff

## Adapt it after creation

- Replace generic work with the agreed deliverables
- Add named owners and client review dates
- Add contract-specific acceptance steps after creation

 How to use this template

## A practical path through the schedule.

- 1

### Establish an approved foundation

 Start at kickoff, gather requirements, and use Requirements approved to clarify what the delivery team is taking forward.

- 2

### Manage the delivery window

 Create the work plan, execute delivery, and run a midpoint review before the Delivery ready milestone.

- 3

### Finish with acceptance and handoff

 Keep client review, revisions, approval, and handoff linked so the final delivery path remains clear to the team and client.

 Not included

## Planning aid

 This template is a planning aid and does not replace client contracts, acceptance criteria, or professional advice.

- Client contacts and members
- Contracts
- Credentials
- Invoices
- Payment details
- Private deliverables and files
- Time billing

 Template FAQ

## Answers before you start.

 What does this client delivery plan template include? + It includes kickoff, requirements approval, work planning, execution, midpoint review, client review, revisions, client approval, and handoff.

 Is this template suitable for a client-facing project? + Yes. It is designed for teams that need a clear sequence from discovery through acceptance, while leaving the project-specific deliverables and client details for the private project.

 What should I add after creating the delivery plan? + Add the agreed deliverables, named owners, client review dates, and any contract-specific acceptance steps that apply to the engagement.

 Related templates

## Close cousins.

 [Templates →](https://ganttfather.com/templates/)

 [Software & technology 19 working days Software Release Timeline Plan a software release from scope through deployment with a practical 19-working-day schedule.](https://ganttfather.com/templates/software-release-timeline/)[Events & experiences 26 working days Event Planning Timeline Plan an event from goals and venue through readiness, event day, follow-up, and retrospective.](https://ganttfather.com/templates/event-planning-timeline/)

 ![](https://ganttfather.com/logo.png)

## Ready to adapt this schedule?

 Create an editable project, set a real start date, and make the plan your own.

 [Use this template free](https://app.ganttfather.com/projects/new?template=client-delivery&entry=template-library) Your first project is included. Existing accounts stay subject to their available project capacity.