# Agency website project

[Professional services](https://ganttfather.com/templates/#professional-services) Project timeline template

# Agency website project

 Best for delivering one client website through approved strategy, production, client validation, and launch handoff.

 Best for delivering one client website through approved strategy, production, client validation, and launch handoff.

 [Use the Agency website project template free](https://app.ganttfather.com/projects/new?template=agency-website-project&entry=template-library)

 Put Run agency project kickoff and Agency website project complete on one agreed path.

## Agency website project: make the path from Run agency project kickoff to Agency website project complete visible.

# Agency website project: make the path from Run agency project kickoff to Agency website project complete visible.

 This Agency website project template makes the client-facing path from Run agency project kickoff to Agency website project complete explicit. It keeps each working phase visible so the team can prepare decisions and handoffs before the next commitment is due.

 The public starter remains intentionally clean. Add client files, commercial detail, credentials, and confidential evidence only after creating a private project.

 Included schedule

## 16 rows, 10 links, already sequenced.

 Explore the schedule to connect Run agency project kickoff and Agency website project complete.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 Week 5

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 19 Day

 20 Day

 21 Day

 22 Day

 23 Day

 24 Day

 25 Day

 Define website sitemap

 Create content production plan

 Create visual direction

 Build page templates

 Integrate approved content

 Run staging review

 Run client website validation

 Relative days show the order for Agency website project; set one real start date after creation.

 Read-only shared Gantt preview. Focus a bar and press Enter to inspect it.

 Schedule details

### Complete schedule table

 Put Run agency project kickoff and Agency website project complete on one agreed path.

 Work item Type Schedule Duration Depends on

 Plan website delivery Phase Days 1–6 Derived rollup —

 Run agency project kickoff Task Day 1 1 working day —

 Define website sitemap Task Days 2–3 2 working days Run agency project kickoff

 Create content production plan Task Days 4–5 2 working days Define website sitemap

 Website brief approved Milestone Day 6 Milestone Create content production plan

 Design and build Phase Days 7–20 Derived rollup —

 Create visual direction Task Days 7–9 3 working days —

 Build page templates Task Days 10–14 5 working days Create visual direction

 Integrate approved content Task Days 15–17 3 working days Build page templates

 Run staging review Task Days 18–19 2 working days Integrate approved content

 Website ready for client validation Milestone Day 20 Milestone Run staging review

 Validate and launch Phase Days 21–25 Derived rollup —

 Run client website validation Task Days 21–22 2 working days —

 Complete website launch Task Day 23 1 working day Run client website validation

 Review launch handoff Task Day 24 1 working day Complete website launch

 Agency website project complete Milestone Day 25 Milestone Review launch handoff

## Who it helps

- Teams delivering a defined agency website project
- Project leads who need explicit ownership, decisions, and timing with a client

## What is included

- Plan website delivery: Run agency project kickoff → Define website sitemap → Create content production plan → Website brief approved.
- Design and build: Create visual direction → Build page templates → Integrate approved content → Run staging review → Website ready for client validation.
- Validate and launch: Run client website validation → Complete website launch → Review launch handoff → Agency website project complete.

## Adapt after creation

- This public planning aid contains no confidential client, contract, financial, or production material. Add protected details only inside your secured project.
- Relative days show the order for Agency website project; set one real start date after creation.
- Keep the Agency website project scope, owners, and decisions aligned before client commitments move forward.

 How to use this template

## Agency website project: make the path from Run agency project kickoff to Agency website project complete visible.

- 1

### Plan website delivery

 Sequence Run agency project kickoff → Define website sitemap → Create content production plan → Website brief approved so the next handoff is clear.

- 2

### Design and build

 Sequence Create visual direction → Build page templates → Integrate approved content → Run staging review → Website ready for client validation so the next handoff is clear.

- 3

### Validate and launch

 Sequence Run client website validation → Complete website launch → Review launch handoff → Agency website project complete so the next handoff is clear.

 Not included

## Planning aid

 This public planning aid contains no confidential client, contract, financial, or production material. Add protected details only inside your secured project.

- Agency contracts
- Client analytics data
- Client brand assets
- Domain and DNS access
- Production content
- Website credentials

 Template FAQ

## Good to know

 What does this Agency website project template include? + It sequences Plan website delivery, Design and build, Validate and launch around named work, dependencies, and decision points.

 Who should use this Agency website project plan? + It supports a team completing one finite client engagement with a visible delivery boundary.

 How should the schedule be adapted? + Set real dates and owners after creation, then add private client material only in the secured project.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Professional services 25 working days Client Delivery Plan Manage discovery, delivery, review, and handoff with a client-facing project timeline.](https://ganttfather.com/templates/client-delivery-plan/)[Professional services 19 working days Freelance client project Best for completing one scoped freelance client project through quote approval, focused production, review, and final handoff.](https://ganttfather.com/templates/freelance-client-project/)

 ![](https://ganttfather.com/logo.png)

## Use the Agency website project template free

 Keep the Agency website project scope, owners, and decisions aligned before client commitments move forward.

 [Use the Agency website project template free](https://app.ganttfather.com/projects/new?template=agency-website-project&entry=template-library) Put Run agency project kickoff and Agency website project complete on one agreed path.