# Accreditation preparation

[Education](https://ganttfather.com/templates/#education) Project timeline template

# Accreditation preparation

 Best for completing one bounded accreditation preparation project with a visible sequence of decisions and handoffs.

 Best for organizing one accreditation review preparation cycle through evidence mapping and internal readiness review.

 [Use this template free: Accreditation preparation](https://app.ganttfather.com/projects/new?template=accreditation-preparation&entry=template-library)

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

## Accreditation preparation: How to use this template.

## Accreditation preparation: How to use this template.

 Best for completing one bounded accreditation preparation project with a visible sequence of decisions and handoffs.

### Map accreditation scope

 Map stated review standards, Prepare evidence collection plan, Accreditation scope recorded

### Prepare evidence package

 Inventory available evidence, Record evidence gaps, Prepare internal review package, Evidence package ready for internal review

### Review readiness

 Run internal readiness review, Document formal review preparation, Accreditation preparation package complete

 Adapt after creation

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

 Schedule

## 13 Rows, 8 Dependencies.

 Accreditation preparation: Best for completing one bounded accreditation preparation project with a visible sequence of decisions and handoffs.

 Read-only preview Milestone

 Week 1

 Week 2

 Week 3

 Week 4

 1 Day

 2 Day

 3 Day

 4 Day

 5 Day

 6 Day

 7 Day

 8 Day

 9 Day

 10 Day

 11 Day

 12 Day

 13 Day

 14 Day

 15 Day

 16 Day

 17 Day

 18 Day

 Map stated review standards

 Prepare evidence collection plan

 Inventory available evidence

 Prepare internal review package

 Record evidence gaps

 Run internal readiness review

 Document formal review preparation

 Relative working days show planned order, not calendar dates.

 Use the interactive schedule to inspect the planned sequence.

 Schedule details

### Schedule details

 Map accreditation scope, Prepare evidence package, Review readiness

 Work item Type Schedule Duration Depends on

 Map accreditation scope Phase Days 1–6 Derived rollup —

 Map stated review standards Task Days 1–3 3 working days —

 Prepare evidence collection plan Task Days 4–5 2 working days Map stated review standards

 Accreditation scope recorded Milestone Day 6 Milestone Prepare evidence collection plan

 Prepare evidence package Phase Days 7–13 Derived rollup —

 Inventory available evidence Task Days 7–9 3 working days —

 Prepare internal review package Task Days 10–12 3 working days Inventory available evidence

 Record evidence gaps Task Days 10–11 2 working days Inventory available evidence

 Evidence package ready for internal review Milestone Day 13 Milestone Record evidence gaps, Prepare internal review package

 Review readiness Phase Days 14–18 Derived rollup —

 Run internal readiness review Task Days 14–15 2 working days —

 Document formal review preparation Task Days 16–17 2 working days Run internal readiness review

 Accreditation preparation package complete Milestone Day 18 Milestone Document formal review preparation

## Who this helps

- Who this helps
- Education Planning team

## What is included

- Map accreditation scope: Map stated review standards → Accreditation scope recorded
- Prepare evidence package: Inventory available evidence → Evidence package ready for internal review
- Review readiness: Run internal readiness review → Accreditation preparation package complete

## Adapt after creation

- Relative working days show planned order, not calendar dates.
- Not included: Student records, Confidential evidence.

 How to use this template

## Accreditation preparation: How to use this template

- 1

### Map accreditation scope

 Map stated review standards, Prepare evidence collection plan, Accreditation scope recorded

- 2

### Prepare evidence package

 Inventory available evidence, Record evidence gaps, Prepare internal review package, Evidence package ready for internal review

- 3

### Review readiness

 Run internal readiness review, Document formal review preparation, Accreditation preparation package complete

 Not included

## Planning boundary

 This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

- Confidential evidence
- Private gap assessments
- Reviewer identities
- Student records
- Submission credentials

 Frequently asked questions

## Good to know

 Accreditation preparation: Frequently asked questions + What is included: Map accreditation scope, Prepare evidence package, Review readiness.

 Good to know + This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.

 Related templates

## Related templates

 [Templates →](https://ganttfather.com/templates/)

 [Education 14 working days Online course launch Best for completing one bounded online course launch project with a visible sequence of decisions and handoffs.](https://ganttfather.com/templates/online-course-launch/)[Education 15 working days Academic semester planning Best for completing one bounded academic semester planning project with a visible sequence of decisions and handoffs.](https://ganttfather.com/templates/academic-semester-planning/)

 ![](https://ganttfather.com/logo.png)

## Ready to adapt this plan?

 Relative working days show planned order, not calendar dates.

 [Use this template free: Accreditation preparation](https://app.ganttfather.com/projects/new?template=accreditation-preparation&entry=template-library) This public planning template is a starting point. Add sensitive details only in your protected project and follow your organisation’s processes.