# Microsoft Planner vs Project vs To Do: Which Tool Do You Need in 2026? | GanttFather Blog

# Microsoft Planner vs Project vs To Do: Which Tool Do You Need in 2026?

 Use Microsoft To Do for personal daily tasks, Planner for shared team work, Planner Plan 1 for web Gantt scheduling, and Planner and Project Plan 3 when you need baselines, critical path, advanced dependencies, or Project desktop.

 ![](https://ganttfather.com/logo.png) GanttFather

 Updated August 7, 2026 18 min read

 Tags

 microsoft-planner microsoft-project microsoft-to-do comparison microsoft-365

 The short answer

 Use Microsoft To Do for personal daily tasks, Planner for shared team work, Planner Plan 1 for web Gantt scheduling, and Planner and Project Plan 3 when you need baselines, critical path, advanced dependencies, or Project desktop.

## Should you use Microsoft To Do, Planner, or Project?

 **Use Microsoft To Do for personal tasks and daily focus; use basic Microsoft Planner for shared team boards; use Planner Plan 1 for a web-based Gantt timeline and finish-to-start dependencies; use Planner and Project Plan 3 for baselines, critical path, advanced dependencies with lead/lag, portfolios, and the Project desktop app.**

 Microsoft’s naming now overlaps. The former Project for the web capabilities are being delivered through premium Planner, while Project desktop remains a distinct Windows scheduling application. Project Online is a separate legacy service and is scheduled to retire on **September 30, 2026**; its retirement does not remove Project desktop or Planner.

 **Products, U.S. list prices, and retirement dates verified:** August 7, 2026.

## What is the simplest difference between the three tools?

 Product or tier Primary job Typical user Gantt / Timeline Dependencies Current U.S. list price

 Microsoft To Do Personal lists, reminders, My Day Individual No No Free / included with Microsoft accounts

 Planner in Microsoft 365 Shared task boards and team coordination Team member No Timeline view Cannot create dependencies Included in eligible Microsoft 365 plans

 Planner Plan 1 Structured web project plan Team lead / project manager Yes Create dependencies; pricing page specifies finish-to-start $10/user/month, paid yearly

 Planner and Project Plan 3 Advanced web scheduling plus Project desktop Professional scheduler / PMO Yes Advanced types with lead and lag $30/user/month, paid yearly

 “Microsoft Project” can mean Project desktop, the retiring Project Online service, or older references to Project for the web. When requesting a license, name the exact application and capability instead of asking for “Project.”

## When is Microsoft To Do the right choice?

 Microsoft To Do is for one person’s work: daily lists, reminders, recurring tasks, steps, flagged Outlook email, and a My Day shortlist. Lists can be shared, but To Do does not provide a team project board, dependency network, resource plan, baseline, or Gantt chart.

 Choose To Do when the question is “What must I finish today?” rather than “How do 40 tasks determine a delivery date?” Microsoft also surfaces tasks assigned to a person from Planner in To Do’s **Assigned to you** experience, so To Do can be the personal inbox while Planner remains the team system.

 To Do strength To Do limitation

 Fast personal capture No project hierarchy

 My Day and reminders No Gantt chart

 Outlook flagged-email integration No dependency scheduling

 Shareable simple lists Weak portfolio and team reporting

 Personal and work accounts Not a substitute for a controlled project schedule

## When is basic Microsoft Planner the right choice?

 Basic Planner is a collaborative task board included in eligible Microsoft 365 business, enterprise, and education subscriptions. It gives teams Grid, Board, Schedule, and Charts views, buckets, assignments, checklists, labels, attachments, notifications, and integration with Teams and Microsoft 365 groups.

 Use basic Planner for campaigns, recurring team processes, small internal projects, and visible ownership when due dates are mostly independent. Basic Planner works best when the plan can tolerate manual date updates and does not need a calculated finish date.

 Basic Planner does **not** let a user create dependencies or open Timeline (Gantt), People, and Goals views. A basic-license user can still edit ordinary task details in a premium plan created by a licensed user, but Microsoft requires a paid Planner license to access premium views and advanced capabilities.

## When is Planner Plan 1 the right choice?

 Planner Plan 1 is the first premium web tier. It adds Timeline (Gantt), Calendar and People views, task dependencies, milestones, goals, sprints and backlogs, subtasks, and custom task fields.

 Choose Plan 1 when the team wants web-based scheduling inside Teams and Microsoft 365 without installing Project desktop. It fits moderately complex plans that need a visual task chain but do not require the deeper baseline, critical-path, advanced lead/lag, assignment, or desktop controls reserved for Plan 3.

 Microsoft’s current pricing page describes Plan 1 dependencies as **finish-to-start**. Another broad Planner support page describes advanced FS, SS, FF, and SF scheduling in premium Planner, but packaging varies by license. Treat Plan 1 as the FS-focused tier unless the intended tenant demonstrates other types under its assigned license.

## When do you need Microsoft Project or Plan 3?

 Choose **Planner and Project Plan 3** when a schedule must be measured and controlled, not merely displayed. The current plan includes:

- baselines and critical path;

- advanced dependencies with lead and lag;

- task history and Assignments view;

- portfolio creation;

- the Project desktop app for up to five PCs per licensed user;

- access to Project Online until that service retires.

 Project desktop remains the choice for schedulers who need mature desktop planning, detailed resource and cost fields, extensive reports, multiple baselines, and established .mpp workflows. Microsoft documents up to 11 baseline sets in Project desktop.

 Plan 3 does not mean every collaborator needs every advanced control. Microsoft says users with Planner in Microsoft 365 can edit basic task details in plans created by paid users, while advanced views require the corresponding paid license. Model the actual scheduler, editor, and viewer roles before multiplying the list price by the whole company.

## How do their project-management capabilities compare?

 Capability To Do Planner basic Planner Plan 1 Planner and Project Plan 3 / desktop

 Personal My Day Excellent Aggregates assigned work Aggregates assigned work Aggregates assigned work where supported

 Shared team board Shared lists only Yes Yes Yes

 Grid / Board / Charts No Yes Yes Yes

 Timeline / Gantt No No Yes Yes

 Create dependencies No No Yes, FS-focused packaging Yes, advanced types with lead/lag

 Critical path No No No in Plan 1 pricing Yes

 Baseline No No No in Plan 1 pricing Yes

 Milestones No No Yes Yes

 Resource / People view No No People view People + Assignments; desktop has deeper resource controls

 Portfolio creation No No View portfolios Create portfolios

 Desktop application To Do apps, not Project Web / Teams Web / Teams Project desktop included

 Best for One person’s next actions Lightweight team execution Structured web schedules Advanced schedule and portfolio control

 For a focused two-way comparison, see [Microsoft Planner vs Microsoft Project](https://ganttfather.com/article/microsoft-planner-vs-microsoft-project-2026/). If the missing feature is specifically Gantt, read [Does Microsoft Planner have a Gantt chart?](https://ganttfather.com/article/does-microsoft-planner-have-gantt-chart/).

## What changed with Project for the web?

 Microsoft has been combining the simplicity of To Do, team collaboration from Planner, and Project for the web capabilities in the new Planner experience. Consequently, a help page may still say “Project for the web” while the current product and pricing surface calls the same class of capabilities premium Planner.

 This does not make Project desktop disappear. It means buyers should distinguish:

- **Premium Planner in the browser or Teams**—the successor surface for Project for the web capabilities.

- **Project desktop**—the installed scheduling client included with Plan 3 and higher.

- **Project Online**—the SharePoint-based enterprise service retiring September 30, 2026.

- **Project Server Subscription Edition**—an on-premises product not covered by this comparison.

 If an integration or procurement document says only “Microsoft Project,” ask which of those four it means.

## What does the Project Online retirement mean in 2026?

 Project Online remains available to existing eligible customers until September 30, 2026, but new Project Web App site creation was blocked starting April 1, 2026. Microsoft says only Project Online is retiring; Project desktop, Project Server Subscription Edition, and Planner basic/premium are not retired by that announcement.

 Organizations still using Project Online should treat migration as current work, not a future roadmap item. Inventory PWA sites, custom workflows, integrations, reports, resource pools, and portfolio processes before choosing premium Planner, Project desktop/Server, or another platform. A license with Project Online access is not a reason to start a new long-term Project Online deployment weeks before retirement.

## What are the clearest signs that basic Planner is no longer enough?

 Upgrade or compare alternatives when two or more of these conditions are true:

- One delayed task should automatically affect downstream dates.

- Stakeholders ask for a Gantt chart rather than a calendar or board.

- The team needs milestones and a calculated critical path.

- Approved dates must be frozen in a baseline and compared with current dates.

- Resource effort and allocation must be planned, not merely assigned.

- Multiple plans need portfolio-level reporting.

- Audit history and advanced task fields are mandatory.

- A professional scheduler must work in Project desktop or exchange .mpp files.

 Plan 1 resolves the first two and adds structured web-planning features. Plan 3 targets the full control set. Do not buy Plan 3 solely because someone said “we need Project” if a basic board or Plan 1 Timeline solves the actual need.

## What should you choose when Microsoft licensing is not the best fit?

 Stay with Microsoft when Teams, Microsoft 365 groups, Entra identity, Power Automate, and familiar administration outweigh license complexity. The integrated ecosystem is the main advantage.

 Compare a dedicated scheduler when most collaborators only need to view a plan, the first project must be free, or the team wants a Gantt-first interface without mixing basic and premium Planner plan types. GanttFather’s free tier includes one owned project with two editor seats and unlimited viewers and guests, along with dependency types and critical-path access in the application. It does not replace Project desktop’s mature cost, macro, and enterprise scheduling depth.

 See [GanttFather vs Microsoft Planner](https://ganttfather.com/vs/microsoft-planner/) for a product-level decision and [Microsoft Project vs monday.com](https://ganttfather.com/article/microsoft-project-vs-monday-2026/) if the alternative is a broad work-management platform.

## Which Microsoft tool fits common real-world scenarios?

 Scenario Best starting point Why

 Personal weekly priorities and flagged email Microsoft To Do Fast capture, My Day, reminders

 Five-person team tracking independent tasks Planner basic Shared board inside Microsoft 365

 Marketing launch with dependent dates and milestones Planner Plan 1 Web Gantt and structured team schedule

 Construction or engineering schedule with baseline variance Planner and Project Plan 3 / Project desktop Baselines, critical path, advanced dependency control

 PMO portfolio with professional schedulers Plan 3 or Plan 5 evaluation Portfolio and advanced scheduling; validate governance needs

 Existing Project Online tenant Migration program now Service retires September 30, 2026

 Executives need view-only Gantt access without advanced Microsoft licenses Dedicated Gantt comparison Viewer economics may favor another tool

 Start with the smallest tool that protects the project’s critical invariant. A personal list should not become a PMO platform, and a contractual integrated master schedule should not be managed as independent cards.

## When is GanttFather simpler than Planner or Project?

 Choose GanttFather when a few people need to build a dependency-driven schedule while many stakeholders only need live visibility. Its free tier includes one owned project with two editor seats and unlimited viewers and guests, plus FS, SS, FF, and SF dependencies with lag, critical path, Excel import/export, and real-time sharing without mixing basic and premium Planner views.

 GanttFather does not replace Project desktop’s .mpp ecosystem, multiple baselines, automatic resource leveling, cost controls, or Microsoft 365 administration, and it has no native Planner synchronization. When those controls are unnecessary and viewer economics drive the decision, [create a free GanttFather project](https://ganttfather.com/) and model one representative phase before assigning premium Microsoft licenses.

## What else do people ask about Planner, Project, and To Do?

### Is Microsoft Planner replacing Microsoft Project?

 Premium Planner is absorbing Project for the web capabilities and branding, but it is not eliminating Project desktop. Project Online, a separate SharePoint-based service, retires September 30, 2026. Always distinguish Project for the web, Project desktop, and Project Online.

### Can Microsoft To Do show Planner tasks?

 Yes. Tasks assigned to a user in Planner can appear in To Do’s Assigned to you experience. To Do remains a personal task surface; editing premium fields may require opening the premium plan and holding the appropriate Planner license.

### Does basic Microsoft Planner include a Gantt chart?

 No. Basic Planner includes Grid, Board, Schedule, and Charts views. Timeline—the Gantt view—is a premium feature. Planner Plan 1 is the lowest current standalone Planner tier that lists Timeline access.

### Is Planner Plan 1 the same as Project Plan 1?

 Planner Plan 1 is the current name aligned with Microsoft’s Planner consolidation. Older documents and invoices may refer to Project Plan 1 or Project for the web. Verify the tenant SKU and current feature table instead of relying on the older product label.

### Do all team members need Plan 1 or Plan 3?

 Not for ordinary collaboration. Microsoft says Planner-in-Microsoft-365 users can edit basic task details in a premium plan created by a licensed user. However, Timeline, People, Goals, Assignments, and other advanced capabilities require the applicable paid license for the person using those views.

### Is Project Online still safe to start using?

 No new long-term deployment should start in Project Online now. Microsoft will retire the service on September 30, 2026, and has already restricted new PWA site creation. Existing customers should maintain service continuity while executing a migration plan.

 **Licensing and product status checked:** August 7, 2026. Prices are U.S. list prices with annual billing; taxes, agreements, region, and promotions can change totals.

 **Sources**

- [Microsoft, Planner plans and pricing](https://www.microsoft.com/en-us/microsoft-365/planner/microsoft-planner-business-plans-and-pricing)

- [Microsoft Support, Compare Planner basic vs premium plans](https://support.microsoft.com/en-us/Planner/compare-microsoft-planner-basic-vs-premium-plans)

- [Microsoft Support, To Do vs Planner](https://support.microsoft.com/en-us/todo/to-do-vs-planner)

- [Microsoft Support, Advanced capabilities with premium plans in Planner](https://support.microsoft.com/en-US/Planner/teams/advanced-capabilities-with-premium-plans-in-planner)

- [Microsoft Planner Blog, Microsoft Project Online is retiring](https://techcommunity.microsoft.com/blog/plannerblog/microsoft-project-online-is-retiring-what-you-need-to-know/4450558)

- [Microsoft Support, Create or update a baseline in Project desktop](https://support.microsoft.com/en-us/project/create-or-update-a-baseline-or-an-interim-plan-in-project-desktop)

 ![](https://ganttfather.com/logo-hero.png) Want to skip the reading?

 GanttFather is free forever &mdash; no card, no trial.

[Start free](https://app.ganttfather.com/login)

 Need help?

 Reach out to our team &mdash; we're happy to help.

support@ganttfather.com

 Next up

 [Compare Asana vs ClickUp 2026: Which Project Tool Wins?](https://ganttfather.com/article/asana-vs-clickup-2026/)[Compare Asana vs GanttProject 2026: Cloud Platform vs Free Desktop](https://ganttfather.com/article/asana-vs-ganttproject-2026/)[Compare Asana vs Microsoft Planner 2026: Standalone WM vs M365 Bundled](https://ganttfather.com/article/asana-vs-microsoft-planner-2026/)

 ![](https://ganttfather.com/logo-hero.png) GanttFather

 The Don of Project Management

 Every feature included &mdash; Gantt, Kanban, dependencies, critical path, real-time sync, Excel and AI agents. Free tier includes 1 project you own, 2 editor seats, and unlimited viewers and guests.

[Start free](https://app.ganttfather.com/login)