# How to Turn On and Read the Critical Path in GanttFather | GanttFather Blog

# How to Turn On and Read the Critical Path in GanttFather

 Click Critical Path in the Gantt toolbar to color the longest chain of linked tasks red, then read the red bars, arrows, and parent tints to see which delays move your finish.

 ![](https://ganttfather.com/logo.png) GanttFather

 Updated November 1, 2026 7 min read

 The short answer

 Click Critical Path in the Gantt toolbar to color the longest chain of linked tasks red, then read the red bars, arrows, and parent tints to see which delays move your finish.

 To see the critical path in GanttFather, open the project’s Gantt chart and click **Critical Path** in the toolbar. The chain of linked tasks with no slack turns red: red bars, thick red dependency arrows, and tinted rows. A check mark on the button shows that it is on. Click it again to turn it off.

## Before you start

 The critical path is built from dependencies. Link tasks first, using [the dependencies guide](https://ganttfather.com/article/how-to-set-task-dependencies-in-ganttfather/). Without links between sibling tasks, nothing is highlighted.

## Turn it on

- Open the project and go to the Gantt chart.

- Click **Critical Path** in the toolbar. Its tooltip reads “Show critical path” when it is off.

- Look at the chart. The tooltip now reads “Hide critical path”.

 The question-mark icon next to the button, “What is the critical path?”, opens the explanation on the GanttFather website in a new tab.

 ![GanttFather Gantt chart with Critical Path switched on: the chain from Building permits through Layout and leveling, Excavation, Piles, and Footings is drawn in red with red arrows, and the parent rows are tinted.](https://ganttfather.com/guides/how-to-turn-on-and-read-the-critical-path-in-ganttfather/gantt-critical-path-on.png)

## How to read it

- **Solid red bars:** tasks on the critical path. They have no total float, so a delay to any of them delays the end of their group.

- **Thick red arrows:** the dependency links the path runs through.

- **Red row tint and the “Critical Path” label:** the task row is critical. The same tint shows in the task list on the left.

- **Lighter tint and a dashed red edge on a parent:** the path passes through one of its subtasks, but the parent is not a critical task itself.

- **Plain bars:** tasks with float. They can slip by that amount without moving the end.

 Turn the toggle on in the Gantt toolbar, then open the List view: critical tasks carry a **CP** badge while the toggle is on. The critical path figure in the **Reports** tab reports “N of M tasks on critical path” and is calculated whether or not the toggle is on.

## What happens next

 Use the red chain to decide where effort goes: shorten a red task, split it, or remove an unneeded link. Then watch the path. A different chain can turn red once the first one shortens. For the method behind it, read [the critical path method guide](https://ganttfather.com/article/critical-path-method-guide-project-management/) and [float and slack](https://ganttfather.com/article/float-slack-project-management/).

## How GanttFather calculates it

- It runs in your browser from the planned dates and the dependencies, and recalculates when you change them. Nothing is saved, and the toggle resets when you reload the page.

- All four types (FS, SS, FF, SF) and lag are used.

- Each group of tasks under the same parent is its own small network, and parents act as summaries of their subtasks. The path is therefore worked out per group, and a parent can show the lighter tint.

- A task counts as critical when its total float is zero and it sits on a critical link. A lone task, or two tasks with no link between them, is never marked critical, even though their float is zero.

## Common problems

- **Symptom:** nothing turns red. **Cause:** there are no dependencies between sibling tasks. **Fix:** [link the tasks](https://ganttfather.com/article/how-to-set-task-dependencies-in-ganttfather/).

- **Symptom:** a task is red but not late. **Cause:** critical means no slack, not behind schedule. **Fix:** treat it as a task to protect.

- **Symptom:** the path is gone after reloading. **Cause:** the toggle is not saved. **Fix:** click **Critical Path** again.

- **Symptom:** Reports shows critical tasks while the Gantt chart does not. **Cause:** Reports calculates the path whether or not the toggle is on. **Fix:** turn the toggle on to see them in the chart.

- **Symptom:** an AI assistant connected through MCP lists different critical tasks than the chart. **Cause:** the agent tool get_critical_path looks only at FS links, ignores lag and groups, and treats all tasks as one flat list, while the chart honors all four types, lag, and groups. **Fix:** use the chart as the reference. See [connect Claude to your project schedule](https://ganttfather.com/article/connect-claude-to-project-schedule-mcp/).

## Related guides

- [How to set task dependencies in GanttFather](https://ganttfather.com/article/how-to-set-task-dependencies-in-ganttfather/)

- [How to add tasks and subtasks in GanttFather](https://ganttfather.com/article/how-to-add-tasks-and-subtasks-in-ganttfather/)

- [The critical path method](https://ganttfather.com/article/critical-path-method-guide-project-management/)

- [How to read a Gantt chart](https://ganttfather.com/article/how-to-read-a-gantt-chart/)

- [Project schedule quality checklist](https://ganttfather.com/article/project-schedule-quality-checklist/)

## How do you find the critical path in GanttFather?

 Link your tasks with dependencies, open the Gantt chart, and click Critical Path in the toolbar. The longest chain of linked tasks turns red, with red arrows, so you can see which delays move the finish and which tasks have float.

 [Open GanttFather](https://ganttfather.com/) and turn on the critical path for your own schedule.

## Frequently asked questions

### Why is a single unlinked task never red?

 A task with no link to another task cannot drive anything, so GanttFather does not mark it critical even though its float is zero. Link it to its neighbors and it can join the path.

### Does the critical path change when I change a date or a link?

 Yes. It is recalculated from the current dates and links every time.

### Can I leave the critical path on for the whole team?

 The toggle is not saved. It affects only your own view and resets when the page reloads.

 Want to skip the reading?

 GanttFather is free forever, with no card and no trial.

 [Start free](https://app.ganttfather.com/login)

 Tags

 gantt-chart how-to critical-path schedule-review float

## Next up

 [Product How to Cancel a GanttFather Subscription or Get a Refund](https://ganttfather.com/article/how-to-cancel-ganttfather-subscription/)[Product How to invite people and set roles in GanttFather](https://ganttfather.com/article/how-to-invite-people-and-set-roles-in-ganttfather/)[Product How to Upgrade Your GanttFather Plan or Add Editors](https://ganttfather.com/article/how-to-upgrade-ganttfather-plan/)