# How to move a Microsoft Project schedule into GanttFather | GanttFather Blog

# How to move a Microsoft Project schedule into GanttFather

 Save your .mpp as an Excel workbook, then import it with MS Project format. Lists what carries over (tasks, dates, resources) and what you rebuild (links).

 ![](https://ganttfather.com/logo.png) GanttFather

 Updated November 1, 2026 7 min read

 The short answer

 Save your .mpp as an Excel workbook, then import it with MS Project format. Lists what carries over (tasks, dates, resources) and what you rebuild (links).

 GanttFather cannot open a .mpp file. To move a Microsoft Project schedule, save it from Project as an Excel workbook (File, Save As, Excel Workbook), then in GanttFather click **Import / export**, **Import Excel** and choose **MS Project format**. Task names, the task tree, dates, percent complete and resource names come across. Predecessor links do not, so you add them again in GanttFather.

## Before you start

- You need a project in GanttFather that you can edit. Create an empty one, or import into an existing project.

- You need Microsoft Project to make the Excel file. GanttFather reads .xlsx files only, not .mpp , .xls or .csv .

## How to move the schedule

- In Microsoft Project, open the schedule and choose File, Save As, and save it as an Excel workbook ( .xlsx ). If Project offers to export selected data, export the task table and keep the Task Name, Start, Finish, % Complete and Resource Names columns. Microsoft Project writes the task names indented, one level per four spaces. Do not remove these spaces.

- In GanttFather, open the project and click **Import / export** in the toolbar. The **Data & sync** window opens.

- Click **Import Excel**.

- Choose **MS Project format**.

- Click **Next: View guide**, read it, then click **Next: Upload file**.

- Drop the .xlsx file in the box, or click it to browse.

- On the **Confirm Import** screen, check the **New** tab for the task tree, the **Resources** tab for people that will be created, and **Issues** for warnings. Use **Import into** to put the whole schedule under an existing task.

- Click **Confirm Changes**.

 You see “Import complete” and a count such as “86 tasks created · 0 tasks updated.” The tasks appear in the Gantt, List and Board views.

## What carries over

 From Microsoft Project In GanttFather

 Task Name Task name. The leading spaces set the nesting, four spaces per level.

 Start and Finish Start date and end date.

 % Complete Progress, 0 to 100.

 Resource Names Assignees. Names not found in the project are created as virtual resources.

 Status text Matched to your statuses. “Complete” becomes your done status. Other words, such as “Late”, fall back to the default not-started status.

 Task 0 (project summary row) A normal top-level task.

 GanttFather reads the first sheet of the workbook, whatever its name.

## What does not carry over

- Predecessors and dependency types. The Predecessors column is ignored. Add dependencies in GanttFather after the import.

- Duration, milestone flags, constraints, calendars and the ID , # and outline-number columns.

- Baselines. GanttFather has no baseline feature.

- Priority, notes and custom fields.

 After the import, set up the links between tasks, then turn on the critical path to compare the new dates with your old schedule.

## What happens next

 Before it writes anything, GanttFather saves a restore point named “Before Excel import”. Open **History**, then **Versions**, to go back if the result looks wrong. Only Owners and Admins get the restore point.

 Importing the same Microsoft Project file again does not duplicate the tree. Rows match existing tasks by their position and name, so they show as updated or unchanged. Tasks you delete in Microsoft Project are not deleted in GanttFather.

## Common problems

- **Everything is at the top level.** The file lost its leading spaces, often because the Task Name column was re-saved or trimmed. Export again from Microsoft Project and import the new file.

- **Dates are off by a month or a day.** Dates with a two-digit year are read as month/day/year first. Set the date format in Microsoft Project to a four-digit year before you save, or fix the dates in the file.

- ** Invalid Template: Could not find "Name" or "Nombre" column .** The header row has no Task Name column. Export the task table with the name column included.

- **Statuses all show as not started.** Only words such as Complete, Closed, On hold and In progress are recognized, in English and Spanish. A row at 100% complete with no recognized status is marked as completed.

- **The wrong format was chosen.** A file from Microsoft Project read as **GanttFather format** fails because there is no Project_Plan sheet. Go back and choose **MS Project format**.

## Related guides

- [How to import and export Excel in GanttFather](https://ganttfather.com/article/how-to-import-and-export-excel-in-ganttfather/)

- [How to save and restore a version in GanttFather](https://ganttfather.com/article/how-to-save-and-restore-a-version-in-ganttfather/)

- [Project schedule baseline guide](https://ganttfather.com/article/project-schedule-baseline-guide/)

- [Free alternative to Microsoft Project](https://ganttfather.com/free-microsoft-project-alternative/)

## Can GanttFather work as an alternative to Microsoft Project?

 For many schedules, yes: tasks, hierarchy, dependencies, critical path, resources and real-time sharing are in GanttFather, and you can bring a Microsoft Project plan in through Excel. Before you switch, know the gaps: it has no baselines and cannot open .mpp files.

 Import your task tree first, add the dependencies, and check the critical path against your old plan before you switch.

 [Open a free GanttFather project and import your Microsoft Project tasks](https://ganttfather.com/) to see your schedule on a Gantt chart.

## Frequently asked questions

### Can GanttFather open a .mpp file?

 No. Save the schedule from Microsoft Project as an Excel workbook, then import that .xlsx file with **MS Project format**.

### Do my task links and dependencies come across?

 No. The Predecessors column is ignored. Add the dependencies in GanttFather after the import.

### Are resources imported?

 Resource names are imported as assignees. A name that is not yet in the project is created as a virtual resource, and the **Resources** tab lists these before you confirm.

 Want to skip the reading?

 GanttFather is free forever, with no card and no trial.

 [Start free](https://app.ganttfather.com/login)

 Tags

 microsoft-project mpp excel import migration

## Next up

 [Product How to Cancel a GanttFather Subscription or Get a Refund](https://ganttfather.com/article/how-to-cancel-ganttfather-subscription/)[Product How to invite people and set roles in GanttFather](https://ganttfather.com/article/how-to-invite-people-and-set-roles-in-ganttfather/)[Product How to Upgrade Your GanttFather Plan or Add Editors](https://ganttfather.com/article/how-to-upgrade-ganttfather-plan/)